9027 W MONTE MAR DR 90035

Certificate Information: 9027 W MONTE MAR DR 90035

Application / Permit
22010-10000-05934
Plan Check / Job No.
B22LA24504
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD TWO STORY HOUSE WITH ATTACHED GARAGE + ROOF DECK
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 SERGIO GUTIERREZ
Corrections Issued 12/20/2022 SERGIO GUTIERREZ
Quality Review Completed 12/22/2022 RODOLFO ARIAS
Plan Check Approved 4/13/2023 SERGIO GUTIERREZ
Issued 4/17/2023 APPLICANT
CofO in Progress 3/19/2024 MEL KHACHATOURIAN
Permit Finaled 4/9/2024 DANIEL ORRANTE
CofO Issued 4/9/2024 DANIEL ORRANTE
Permit Finaled 4/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/3/2023 AMAAN MALIK
Hydrant and Access approval Cleared 2/10/2023 KURT CORRAL
Low Impact Development Cleared 3/15/2023 AMMAR ELTAWIL
Eng Process Fee Ord 176,300 Cleared 3/16/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/16/2023 ANTHONY MAINEZ
Sewer availability Cleared 3/16/2023 TREVOR QUAN
GPI Written Notices Cleared 3/30/2023 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 3/30/2023 SERGIO GUTIERREZ

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2023 Approved JEREMY TODD
Footing/Foundation/Slab 5/24/2023 Partial Approval JEREMY TODD
METHANE-Barrier 5/24/2023 Not Ready for Inspection JEREMY TODD
METHANE-Subgrade 5/24/2023 Not Ready for Inspection JEREMY TODD
Underground Mechanical 5/24/2023 Approved JEREMY TODD
Deputy Methane Barrier 6/2/2023 Conditional Approval DAVID FEILER
Deputy Methane Barrier 6/5/2023 Conditional Approval JEREMY TODD
Excavation/Setback/Form/Re-Bar 6/12/2023 Approved JEREMY TODD
Footing/Foundation/Slab 6/12/2023 Approved JEREMY TODD
METHANE-Barrier 6/12/2023 Approved JEREMY TODD
METHANE-Rough 6/12/2023 Approved JEREMY TODD
METHANE-Subgrade 6/12/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval JEREMY TODD
BUILDING-Rough-Frame 6/29/2023 Partial Approval JEREMY TODD
Green Building Rough 6/29/2023 Not Ready for Inspection JEREMY TODD
Verify Sprinkler Sign Off 6/29/2023 Not Ready for Inspection JEREMY TODD
Wood Frame 6/29/2023 Partial Inspection JEREMY TODD
Deputy Wood Construction 8/3/2023 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/9/2023 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 8/22/2023 Corrections Issued DAVID FEILER
PLUMBING-Rough 8/22/2023 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 8/23/2023 No Access for Inspection MEL KHACHATOURIAN
Wood Frame 8/23/2023 No Access for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 8/24/2023 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 8/25/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 8/25/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 8/25/2023 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 8/29/2023 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 8/29/2023 Approved MEL KHACHATOURIAN
Green Building Rough 8/29/2023 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 8/29/2023 Approved MEL KHACHATOURIAN
Insulation 9/5/2023 Approved MEL KHACHATOURIAN
Drywall Nailing 9/11/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 9/11/2023 Approved MEL KHACHATOURIAN
Shower Pan 9/11/2023 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 1/9/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 1/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 1/10/2024 Partial Approval MEL KHACHATOURIAN
Final 2/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 2/23/2024 Approved MEL KHACHATOURIAN
HVAC-Final 2/23/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Final 2/23/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 2/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 2/23/2024 Approved MEL KHACHATOURIAN
Final 3/7/2024 Conditional Approval MEL KHACHATOURIAN
Service/Power Release 3/7/2024 Approved MEL KHACHATOURIAN
Final 3/18/2024 OK to Issue CofO MEL KHACHATOURIAN