607 N MARTEL AVE 90036
Certificate Information: 607 N MARTEL AVE 90036
- Application / Permit
- 22010-10000-05907
- Plan Check / Job No.
- B22LA24438
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD WITH ATTACHED GARAGE (2-STORY)
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | CARLOS MONTES |
| Corrections Issued | 12/11/2022 | CARLOS MONTES |
| Quality Review Completed | 12/12/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/8/2023 | CARLOS MONTES |
| Plan Check Approved | 3/17/2023 | CARLOS MONTES |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 10/25/2024 | JOSE MACIAS |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | CELINA MORENO |
| Sewer availability | Cleared | 1/5/2023 | CELINA MORENO |
| Trees in Parkway | Cleared | 1/18/2023 | ADALBERTO VERA |
| Permit | Cleared | 1/20/2023 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/25/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/25/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | CELINA MORENO |
Contact Information
| Contractor | Fronen Construction Inc; Lic. No.: 1053555-B | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: NA26962 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 7/19/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/7/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Subgrade | 8/7/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/7/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Methane Barrier | 8/14/2023 | Conditional Approval | BRENDAN MORELLI |
| Deputy Methane Barrier | 8/15/2023 | Conditional Approval | LILIANA PORTILLO |
| Deputy Methane Barrier | 8/16/2023 | Conditional Approval | LILIANA PORTILLO |
| Deputy Steel/Welding | 8/22/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/23/2023 | Approved | LILIANA PORTILLO |
| METHANE-Barrier | 8/23/2023 | Approved | LILIANA PORTILLO |
| Deputy Steel/Welding | 9/15/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 10/24/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/24/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 12/18/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/21/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/27/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/16/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/31/2024 | Approved | BRENDAN MORELLI |
| Shower Pan | 2/8/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/27/2024 | Partial Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 2/27/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | AMIR NAZARIAN |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 2/27/2024 | Approved | AMIR NAZARIAN |
| METHANE-Rough | 2/27/2024 | Partial Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 2/27/2024 | Approved | AMIR NAZARIAN |
| Verify Sprinkler Sign Off | 2/27/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 2/27/2024 | Partial Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 3/5/2024 | Conditional Approval | AMIR NAZARIAN |
| Insulation | 3/11/2024 | Conditional Approval | AMIR NAZARIAN |
| Drywall Nailing | 3/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Interior/Exterior Lathing | 3/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Drywall Nailing | 3/21/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 3/21/2024 | Approved | AMIR NAZARIAN |
| Underground Mechanical | 6/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Gas Test | 7/3/2024 | Corrections Issued | AMIR NAZARIAN |
| Grounding or Bonding | 7/3/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 7/3/2024 | Corrections Issued | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 7/3/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Grounding or Bonding | 7/8/2024 | Corrections Issued | AMIR NAZARIAN |
| Deck | 7/11/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | AMIR NAZARIAN |
| Grounding or Bonding | 7/11/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Service/Power Release | 7/11/2024 | Corrections Issued | AMIR NAZARIAN |
| Deck | 7/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Grounding or Bonding | 7/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 7/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Enclosure/Fence | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Grounding or Bonding | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Final | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Service/Power Release | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 7/17/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | AMIR NAZARIAN |
| Gas Test | 8/19/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 8/19/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 8/19/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 8/19/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 8/19/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 8/30/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 8/30/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 8/30/2024 | Partial Approval | ENRIQUE MIRELES |
| Verify Rec and Parks Fee Memo | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/4/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 9/16/2024 | Approved | JOSE MACIAS |
| Final | 9/16/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 9/16/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 9/16/2024 | Approved | JOSE MACIAS |
| HVAC-Final | 9/16/2024 | Approved | JOSE MACIAS |
| METHANE-Final | 9/16/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 9/16/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 9/16/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 9/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 9/16/2024 | Approved | JOSE MACIAS |
| Final | 10/9/2024 | Corrections Issued | JOSE MACIAS |
| Final | 10/23/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 10/23/2024 | Approved | JOSE MACIAS |