114 E DON ST 90744

Certificate Information: 114 E DON ST 90744

Application / Permit
22010-10000-05903
Plan Check / Job No.
B22LA24428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 PRANITA SHAH
Corrections Issued 1/6/2023 PRANITA SHAH
Applicant returned to address corrections 1/28/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 3/14/2023 KEVIN MORALES
Issued 7/18/2023 APPLICANT
CofO in Progress 6/18/2024 EUGENE CASSIDY
Permit Finaled 7/3/2024 ANSON MAGLASANG
CofO Issued 7/3/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/11/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 1/11/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 1/11/2023 ANA SORIANO
Sewer availability Cleared 1/11/2023 ANA SORIANO
Clean Up Green Up Cleared 1/18/2023 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,
Engineer Ruvalcaba,, Martin Eduardo; Lic. No.: C75838 6514 E BRITTAIN ST      LONG BEACH, CA 90808

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2023 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/6/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/6/2023 Approved EUGENE CASSIDY
METHANE-Barrier 11/6/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 11/6/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/14/2023 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 11/14/2023 Partial Approval EUGENE CASSIDY
Insulation 11/21/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/25/2023 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/11/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 12/11/2023 Approved EUGENE CASSIDY
HVAC-Rough 12/11/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 12/11/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 12/11/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 12/11/2023 Approved EUGENE CASSIDY
Deputy Drilled-In Anchors 12/19/2023 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/21/2023 Not Ready for Inspection EUGENE CASSIDY
Insulation 1/8/2024 Approved JOHN KLARIN
Drywall Nailing 1/12/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/12/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/20/2024 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 5/20/2024 Approved EUGENE CASSIDY
Final 6/7/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/7/2024 Not Required EUGENE CASSIDY
Smoke Detectors 6/7/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/17/2024 Approved EUGENE CASSIDY
Final 6/17/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 6/17/2024 Approved EUGENE CASSIDY