3108 3/4 W 27TH ST 90018
Certificate Information: 3108 3/4 W 27TH ST 90018
- Application / Permit
- 22010-10000-05880
- Plan Check / Job No.
- B22LA24369
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1 OF 2 NEW ADU (37' 10" X 10' 11") PER GCS 65852.2(e)(1)(D) AND LAMC12.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | NGHI SU |
| Corrections Issued | 1/6/2023 | NGHI SU |
| Quality Review Completed | 1/18/2023 | KEN GILL |
| Building Plans Picked Up | 1/24/2023 | APPLICANT |
| Applicant returned to address corrections | 3/21/2023 | NGHI SU |
| Plan Check Approved | 9/1/2023 | NGHI SU |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 5/22/2026 | JUSTIN HAWLEY |
| CofO Issued | 5/28/2026 | DEROLD HAUFF |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/2/2023 | RICARDO BOHORQUEZ |
| SB8 RUD | Cleared | 2/6/2023 | JESSICA WANG |
| Address approval | Cleared | 2/9/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/14/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 3/17/2023 | ROGELIO CORTES |
| Construction near power lines | Cleared | 3/18/2023 | RIDWAN HARDY |
| HPOZ | Cleared | 3/28/2023 | DANIEL MATA |
| ZI | Cleared | 3/28/2023 | DANIEL MATA |
| Roof/Waste drainage to street | Cleared | 8/28/2023 | JESSICA OPINION |
Contact Information
| Contractor | Mateos Construction & Remodeling Co; Lic. No.: 1034279-B | 10378 MARKLEIN AVE MISSION HILLS, CA 91345 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 3/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Underground Mechanical | 3/4/2024 | Partial Approval | JUSTIN HAWLEY |
| Pre-Inspection | 3/6/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/8/2024 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 3/8/2024 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 3/8/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/17/2024 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Barrier | 7/17/2024 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Subgrade | 7/17/2024 | Corrections Issued | DAVID FEILER |
| METHANE-Rough | 7/19/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 7/19/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/23/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 7/23/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Subgrade | 7/23/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/24/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Barrier | 7/24/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Subgrade | 7/24/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/19/2024 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 8/19/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 8/19/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 8/23/2024 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/23/2024 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 8/23/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/27/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 8/27/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/27/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 9/4/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/4/2024 | Approved | JUSTIN HAWLEY |
| Final | 11/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 11/26/2025 | Corrections Issued | JUSTIN HAWLEY |
| Final | 4/30/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 5/5/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 5/22/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 5/22/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 5/22/2026 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 5/22/2026 | Approved | JUSTIN HAWLEY |