201 W 62ND ST 90003
Certificate Information: 201 W 62ND ST 90003
- Application / Permit
- 22010-10000-05856
- Plan Check / Job No.
- B22LA24282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2 CAR GARAGE
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | AUNG SOE |
| Corrections Issued | 12/1/2022 | AUNG SOE |
| Plan Check Approved | 12/15/2022 | MINA HABILI |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 6/8/2023 | BRENDAN MORELLI |
| Permit Finaled | 6/15/2023 | DEROLD HAUFF |
| CofO Issued | 6/15/2023 | DEROLD HAUFF |
| Permit Finaled | 6/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 12/7/2022 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/8/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | JEANIE LAM |
Contact Information
| Contractor | C C D L Investments Inc; Lic. No.: 906858-B | 205 AVENIDA DEL MAR #0896 SAN CLEMENTE, CA 92672 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 1/6/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/10/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/13/2023 | Conditional Approval | BRENDAN MORELLI |
| Drywall Nailing | 1/19/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/14/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 3/14/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 3/14/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/14/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV No Gas | BRENDAN MORELLI |
| Service/Power Release | 3/14/2023 | Not Required | BRENDAN MORELLI |
| Smoke Detectors | 3/14/2023 | Approved | BRENDAN MORELLI |
| Final | 4/5/2023 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/24/2023 | Approved | BRENDAN MORELLI |
| Final | 4/24/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 6/7/2023 | OK to Issue CofO | BRENDAN MORELLI |