2808 W EXPOSITION PL 90018

Certificate Information: 2808 W EXPOSITION PL 90018

Application / Permit
22010-10000-05843
Plan Check / Job No.
B22LA24224
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2 STORY ADU PER LAMC 12.22 A.33 (c)-(d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 9/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 MAHNAZ NOURHASHEMI
Corrections Issued 1/3/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 1/10/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/19/2023 APPLICANT
Plan Check Approved 9/1/2023 MAHNAZ NOURHASHEMI
Issued 9/7/2023 APPLICANT
CofO in Progress 1/13/2026 JUSTIN HAWLEY
Permit Finaled 1/14/2026 DEROLD HAUFF
CofO Issued 1/14/2026 DEROLD HAUFF
Permit Finaled 1/14/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2023 TREVOR QUAN
ZI Cleared 1/9/2023 RUBEN VASQUEZ
Hydrant and Access approval Cleared 1/26/2023 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 2/21/2023 TREVOR QUAN
Sewer availability Cleared 2/21/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/23/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2024 Approved JUSTIN HAWLEY
Underground Mechanical 3/25/2025 Corrections Issued JOSE MACIAS
PLUMBING-Rough 4/2/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/10/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved JOSE MACIAS
Green Building Rough 4/30/2025 Not Ready for Inspection JOSE MACIAS
Verify Sprinkler Sign Off 4/30/2025 Not Ready for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Corrections Issued JUSTIN HAWLEY
Green Building Rough 7/7/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 7/7/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 7/18/2025 Approved JUSTIN HAWLEY
Green Building Rough 7/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 7/18/2025 Approved JUSTIN HAWLEY
Underground Mechanical 7/18/2025 Approved JUSTIN HAWLEY
Insulation 7/30/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 7/30/2025 Partial Approval DEVON JACKSON
Drywall Nailing 8/11/2025 Approved JUSTIN HAWLEY
Green Building Rough 8/11/2025 Approved JUSTIN HAWLEY
Shower Pan 8/11/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/10/2025 Approved JUSTIN HAWLEY
Service/Power Release 9/10/2025 Partial Approval JUSTIN HAWLEY
Gas Test 11/5/2025 Approved DEVON JACKSON
Sewer 11/5/2025 Approved DEVON JACKSON
Final 12/15/2025 Corrections Issued JUSTIN HAWLEY
Gas Test 12/15/2025 Approved JUSTIN HAWLEY
Smoke Detectors 12/15/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Not Ready JUSTIN HAWLEY
ELECTRICAL-Final 1/8/2026 Approved JUSTIN HAWLEY
Final 1/8/2026 Corrections Issued JUSTIN HAWLEY
Green Building Final 1/8/2026 Approved JUSTIN HAWLEY
HVAC-Final 1/8/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 1/8/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 1/13/2026 Approved JUSTIN HAWLEY
Final 1/13/2026 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 1/13/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 1/13/2026 Approved JUSTIN HAWLEY
Service/Power Release 1/13/2026 Approved JUSTIN HAWLEY