8227 N LAUREL CANYON BLVD 91605

Certificate Information: 8227 N LAUREL CANYON BLVD 91605

Application / Permit
22010-10000-05837
Plan Check / Job No.
B22LA24202
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per city ordinance
Permit Issued
Issued on 12/30/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/28/2022 RICARDO RAMIREZ
Corrections Issued 12/29/2022 RICARDO RAMIREZ
Building Plans Picked Up 1/10/2023 APPLICANT
Plan Check Approved 12/30/2024 SAMUEL GONZALEZ
Issued 12/30/2024 APPLICANT
CofO in Progress 1/8/2026 MATTHEW NELSON
Permit Finaled 2/5/2026 RUBEN SALAS
CofO Issued 2/5/2026 RUBEN SALAS
Permit Finaled 2/5/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/3/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/3/2023 DAGOVERTO GUERRERO
Construction within easement Cleared 8/22/2023 TINA MIRANDA
Low Impact Development Cleared 10/26/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/13/2023 EDGAR ALCARAZ
Sewer availability Cleared 11/14/2024 CARLOS AGUILERA

Contact Information

Contractor Wynn Builders Inc; Lic. No.: 825806-B 409 N PACIFIC COAST HWY 511      REDONDO BEACH, CA 90277

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2025 Corrections Issued MATTHEW NELSON
Underground Mechanical 3/21/2025 Partial Approval MATTHEW NELSON
Underground Mechanical 3/26/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 4/10/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 6/12/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval MATTHEW NELSON
HVAC-Rough 6/12/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 6/12/2025 Corrections Issued MATTHEW NELSON
Wood Frame 6/12/2025 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved MATTHEW NELSON
HVAC-Rough 6/23/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 6/23/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/2/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 7/2/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/2/2025 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 7/2/2025 Approved MATTHEW NELSON
Wood Frame 7/2/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/15/2025 Approved MATTHEW NELSON
HVAC-Rough 7/15/2025 Approved MATTHEW NELSON
Wood Frame 7/15/2025 Not Ready for Inspection MATTHEW NELSON
Insulation 7/22/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/22/2025 Not Ready for Inspection MATTHEW NELSON
Shower Pan 7/22/2025 Approved MATTHEW NELSON
Drywall Nailing 7/30/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/30/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Ready JAVIER RAMOS JR
ELECTRICAL-Final 1/2/2026 Corrections Issued MATTHEW NELSON
Final 1/2/2026 Corrections Issued MATTHEW NELSON
Green Building Final 1/2/2026 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/2/2026 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 1/2/2026 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 1/2/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 1/7/2026 Approved MATTHEW NELSON
Final 1/7/2026 OK to Issue CofO MATTHEW NELSON
Green Building Final 1/7/2026 Approved MATTHEW NELSON
HVAC-Final 1/7/2026 Approved MATTHEW NELSON
PLUMBING-Final 1/7/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Approved MATTHEW NELSON
Service/Power Release 1/7/2026 Approved MATTHEW NELSON