853 S RIMPAU BLVD 90005

Certificate Information: 853 S RIMPAU BLVD 90005

Application / Permit
22010-10000-05830
Plan Check / Job No.
B22LA24170
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New two-story detached ADU per ordinance 186,481.
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 4/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 HELEN NGUYEN
Corrections Issued 12/12/2022 HELEN NGUYEN
Quality Review Completed 12/30/2022 MICHAEL PEREZ
Applicant returned to address corrections 1/12/2023 HELEN NGUYEN
Applicant returned to address corrections 1/31/2023 HELEN NGUYEN
Applicant returned to address corrections 2/21/2023 HELEN NGUYEN
Applicant returned to address corrections 5/16/2023 HELEN NGUYEN
Plan Check Approved 7/11/2023 HELEN NGUYEN
Issued 9/19/2023 APPLICANT
CofO in Progress 10/27/2024 RONNIE MINDANAO
Permit Finaled 4/5/2025 DEROLD HAUFF
CofO Issued 4/5/2025 DEROLD HAUFF
Permit Finaled 4/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/9/2023 CINDY QI
Sewer availability Cleared 1/9/2023 CINDY QI
Construction near power lines Cleared 2/17/2023 RIDWAN HARDY
Low Impact Development Cleared 5/31/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/14/2023 CINDY QI
Public Works-Sewers Cleared 6/14/2023 CINDY QI
Public Works-Highway Ded. Cleared 6/14/2023 CINDY QI
Public Works-Open Permits Cleared 6/14/2023 CINDY QI

Contact Information

Architect Sheinberg,, Roberto; Lic. No.: C39035 4209 SANTA MONICA BLVD #100      LOS ANGELES, CA 90029
Contractor Building Blocks Ca Llc; Lic. No.: 1034808-B       ,
Engineer Garza,, Omar Leonel; Lic. No.: S5593 600 WILSHIRE BLVD 760      LOS ANGELES, CA 90017
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2023 Partial Approval RICHARD DOCKUS
Sewer 10/20/2023 Approved RICHARD DOCKUS
Deputy Methane Barrier 10/23/2023 Conditional Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 10/26/2023 Approved JUSTIN HAWLEY
METHANE-Rough 10/26/2023 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 1/3/2024 Corrections Issued BRENDAN MORELLI
Underground Mechanical 1/3/2024 Not Ready for Inspection BRENDAN MORELLI
Deputy Methane Barrier 1/24/2024 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 2/14/2024 Corrections Issued RICHARD DOCKUS
METHANE-Final 2/14/2024 Not Ready for Inspection RICHARD DOCKUS
METHANE-Rough 2/14/2024 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 2/14/2024 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Partial Approval RICHARD DOCKUS
HVAC-Rough 2/22/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 3/1/2024 Approved RICHARD DOCKUS
ELECTRICAL-Rough 3/1/2024 Approved RICHARD DOCKUS
METHANE-Rough 3/1/2024 Approved RICHARD DOCKUS
Shower Pan 3/1/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 3/15/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 3/18/2024 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 3/19/2024 Partial Approval AMIR NAZARIAN
Insulation 4/17/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 4/17/2024 Corrections Issued JOSH MEISTER
Interior/Exterior Lathing 4/22/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 4/23/2024 Approved RONNIE MINDANAO
Drywall Nailing 5/3/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 9/30/2024 Corrections Issued RONNIE MINDANAO
Final 9/30/2024 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 9/30/2024 Approved RONNIE MINDANAO
METHANE-Barrier 9/30/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 9/30/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 9/30/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 9/30/2024 Not Ready for Inspection RONNIE MINDANAO
Drywall Nailing 10/3/2024 Approved RONNIE MINDANAO
Drywall Nailing 10/8/2024 Approved RONNIE MINDANAO
Final 10/8/2024 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved RONNIE MINDANAO
Service/Power Release 10/8/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 10/8/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 10/15/2024 Not Ready for Inspection ENRIQUE MIRELES
Final 10/15/2024 Corrections Issued ENRIQUE MIRELES
HVAC-Final 10/15/2024 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 10/15/2024 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 10/15/2024 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 10/15/2024 Partial Approval ENRIQUE MIRELES
Final 10/17/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 10/21/2024 No Access for Inspection RONNIE MINDANAO
Final 10/21/2024 Not Ready for Inspection RONNIE MINDANAO
Service/Power Release 10/21/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 10/21/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 10/23/2024 Approved RONNIE MINDANAO
HVAC-Final 10/23/2024 Approved RONNIE MINDANAO
PLUMBING-Final 10/23/2024 Approved RONNIE MINDANAO
Service/Power Release 10/23/2024 Approved RONNIE MINDANAO
Final 10/25/2024 OK to Issue CofO RONNIE MINDANAO
Service/Power Release 10/25/2024 Approved RONNIE MINDANAO