1243 1/2 S MEADOWBROOK AVE 90019
Certificate Information: 1243 1/2 S MEADOWBROOK AVE 90019
- Application / Permit
- 22010-10000-05809
- Plan Check / Job No.
- B22LA24078
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF (43'-9"x33'-2"), 1149 SQFT 2-STORY ADU ATTACHED TO THE (E) DETACHED 3-CAR GARAGE (510 SQFT), PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | PETER MOSESIAN |
| Corrections Issued | 1/6/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/6/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/11/2023 | PETER MOSESIAN |
| Plan Check Approved | 4/21/2023 | PETER MOSESIAN |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 7/25/2024 | RONNIE MINDANAO |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
| CofO Issued | 12/12/2024 | DEROLD HAUFF |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 1/23/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 3/9/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | TREVOR QUAN |
| HPOZ | Cleared | 4/6/2023 | AMANDA KAINER |
| Construction near power lines | Cleared | 4/14/2023 | OSCAR CASTRO |
Contact Information
| Contractor | Gold Pacific Construction Inc; Lic. No.: 1024672-B | 1134 W 68TH ST LOS ANGELES, CA 90044 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 5/22/2023 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 5/22/2023 | Corrections Issued | RICHARD DOCKUS |
| Deputy Methane Barrier | 5/23/2023 | Conditional Approval | RICHARD DOCKUS |
| METHANE-Subgrade | 5/25/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/25/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/30/2023 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 5/30/2023 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 5/30/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/30/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 7/28/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/7/2023 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/15/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/2/2023 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 10/2/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 10/2/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 10/2/2023 | Approved | RICHARD DOCKUS |
| Sewer | 10/2/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 10/13/2023 | Corrections Issued | RICHARD DOCKUS |
| Drywall Nailing | 10/23/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 11/30/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | RONNIE MINDANAO |
| Final | 3/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 3/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 3/14/2024 | Approved | RONNIE MINDANAO |
| Final | 3/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 3/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 5/15/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 5/15/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | RONNIE MINDANAO |
| Final | 6/21/2024 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 6/21/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/24/2024 | Approved | RONNIE MINDANAO |
| Final | 7/24/2024 | OK to Issue CofO | RONNIE MINDANAO |
| HVAC-Final | 7/24/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 7/24/2024 | Approved | RONNIE MINDANAO |