5171 W PACKARD ST 90019

Certificate Information: 5171 W PACKARD ST 90019

Application / Permit
22010-10000-05807
Plan Check / Job No.
B22LA24075
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 4/20/2023
Issuing Office
Current Status
Issued on 4/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 DANIEL YIP
Corrections Issued 12/19/2022 DANIEL YIP
Applicant returned to address corrections 12/29/2022 DANIEL YIP
Plan Check Approved 1/6/2023 DANIEL YIP
Issued 4/20/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/28/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 12/28/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/5/2023 CELINA MORENO
Sewer availability Cleared 1/5/2023 CELINA MORENO

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/31/2023 Corrections Issued JOSE AVILA
METHANE-Barrier 5/31/2023 Approved JOSE AVILA
METHANE-Subgrade 5/31/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 6/5/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/2/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/2/2023 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 8/7/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 8/16/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/16/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 8/16/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 8/16/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 8/21/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 8/22/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 8/30/2023 Partial Approval JOSE AVILA
Green Building Rough 8/30/2023 Approved JOSE AVILA
METHANE-Rough 8/30/2023 Approved JOSE AVILA
HVAC-Rough 9/14/2023 Approved JOSE AVILA
PLUMBING-Rough 9/14/2023 Approved JOSE AVILA
Drywall Nailing 9/19/2023 Partial Approval RONNIE MINDANAO
ELECTRICAL-Rough 9/19/2023 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 11/14/2023 Approved JOSE AVILA
Drywall Nailing 11/14/2023 Approved JOSE AVILA
ELECTRICAL-Rough 11/14/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 11/14/2023 Approved JOSE AVILA
Final 11/20/2023 No Access for Inspection ALIZAH MAYAGOITIA
Final 12/1/2023 Corrections Issued JOSE AVILA
Green Building Final 12/1/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Not Ready JOSE AVILA
Smoke Detectors 12/1/2023 Approved JOSE AVILA