1374 S BECKWITH AVE 90049
Certificate Information: 1374 S BECKWITH AVE 90049
- Application / Permit
- 22010-10000-05800
- Plan Check / Job No.
- B22LA24049
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: PROPOSED 1 STORY SFD WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 1/12/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/1/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/22/2023 | CRYSTEL MAALOUF |
| Issued | 5/22/2023 | APPLICANT |
| CofO in Progress | 8/7/2024 | ARAM AVEDISIAN |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
| CofO Issued | 8/14/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/1/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | JASON NG |
| Permit | Cleared | 2/2/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 3/11/2023 | RUEL COLE |
| Low Impact Development | Cleared | 3/28/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/31/2023 | DINAH GARIN |
| GPI Written Notices | Cleared | 5/22/2023 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 5/22/2023 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Ingenuity Builders Inc; Lic. No.: 1057002-B | , |
| Contractor | Ingenuity Builders; Lic. No.: 1057002-B | , |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
| Engineer | Mar,, Larry Lee; Lic. No.: C55069 | 4425 BEULAH DR LA CANADA, CA 91011 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/14/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/1/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 9/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 10/10/2023 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 10/17/2023 | Partial Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 10/18/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 10/18/2023 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 10/26/2023 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 11/13/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/13/2023 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 11/13/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 11/16/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 11/17/2023 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 11/17/2023 | Partial Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/22/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 12/5/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 12/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 12/22/2023 | Approved | KENNETH NAGLE |
| Shower Pan | 12/26/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/8/2024 | Partial Approval | ARAM AVEDISIAN |
| Pre-Inspection | 2/23/2024 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/10/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 5/2/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/8/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/10/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/13/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/17/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 5/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 5/17/2024 | Approved | ARAM AVEDISIAN |
| Final | 5/22/2024 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/22/2024 | Approved | ARAM AVEDISIAN |
| Green Building Final | 5/22/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 5/22/2024 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 7/8/2024 | Approved | ARAM AVEDISIAN |
| Final | 8/7/2024 | OK to Issue CofO | ARAM AVEDISIAN |