3459 S COLONIAL AVE 90066
Certificate Information: 3459 S COLONIAL AVE 90066
- Application / Permit
- 22010-10000-05772
- Plan Check / Job No.
- B22LA23950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: New detached ADU 31'-0" x 28'-3" per LAMC 12.22A.33 (c)-(d)
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | NGHI SU |
| Corrections Issued | 12/24/2022 | NGHI SU |
| Quality Review Completed | 12/29/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/21/2023 | NGHI SU |
| Applicant returned to address corrections | 7/19/2023 | NGHI SU |
| Plan Check Approved | 8/10/2023 | NGHI SU |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 11/14/2024 | JESUS PINEDA |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2023 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2023 | SAUL GARCIA |
| Sewer availability | Cleared | 1/27/2023 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 2/1/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 2/1/2023 | ALESSANDRO MERCURI |
| Construction near power lines | Cleared | 2/28/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/28/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/30/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/6/2023 | JASON NG |
| GPI Written Notices | Cleared | 8/9/2023 | NGHI SU |
Contact Information
| Contractor | Klapproth Danielle; Lic. No.: 841982-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/13/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 9/13/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/20/2023 | Approved | RICHARD STEINBACH |
| Sewer | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 10/12/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 12/26/2023 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 1/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/11/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 1/26/2024 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 2/7/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 2/7/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/7/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/18/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/18/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/18/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/18/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 4/10/2024 | No Access for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 4/12/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/18/2024 | Approved | BOBBY KEY |
| Shower Pan | 7/18/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| Final | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 11/4/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 11/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 11/13/2024 | Approved | JESUS PINEDA |
| Final | 11/13/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 11/13/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/13/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 11/13/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 11/13/2024 | Approved | JESUS PINEDA |