16800 W MOONCREST DR 91436

Certificate Information: 16800 W MOONCREST DR 91436

Application / Permit
22010-10000-05759
Plan Check / Job No.
B22LA23871
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW 2-STORY SFD W/ ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 11/6/2023
Issuing Office
Current Status
Issued on 11/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 MAHNAZ NOURHASHEMI
Corrections Issued 2/24/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 3/2/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/19/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 10/13/2023 MAHNAZ NOURHASHEMI
Issued 11/6/2023 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 2/23/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 2/23/2023 MAHNAZ NOURHASHEMI
BHO/Hillside ordinance Cleared 3/6/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/6/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/6/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/6/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/6/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/7/2023 CARLOS AGUILERA
Sewer availability Cleared 3/7/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/12/2023 KURT CORRAL
Trees in Parkway Cleared 3/28/2023 ADALBERTO VERA
Stormwater Pollution Mitigatn Cleared 8/24/2023 MELINEH AGHAKHABIAN
Permit Cleared 8/26/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/26/2023 CARLOS AGUILERA

Contact Information

Contractor Cohen Ben; Lic. No.: 894370-B       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 17514 VENTURA BLVD.   SUITE 206    ENCINO, CA 91346

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/14/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 6/21/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 6/25/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/28/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/9/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 8/13/2024 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/18/2024 Approved THOMAS FINNILA
Deputy Reinf. Concrete 9/19/2024 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 11/5/2024 Conditional Approval THOMAS FINNILA
Wood Frame 11/8/2024 Corrections Issued THOMAS FINNILA
Wood Frame 5/20/2025 Corrections Issued JOHN COLEMAN
Deputy Wood Construction 5/21/2025 Partial Approval SEAN WIRCH
Wood Frame 5/27/2025 Partial Approval THOMAS FINNILA
PLUMBING-Rough 7/22/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/19/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 8/28/2025 Conditional Approval THOMAS FINNILA
HVAC-Rough 10/17/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Corrections Issued JOHN KIDWELL
HVAC-Rough 12/15/2025 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 1/20/2026 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 2/23/2026 Approved MORRIS JACKSON
BUILDING-Rough-Frame 2/26/2026 Corrections Issued THOMAS FINNILA
Verify Sprinkler Sign Off 2/26/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/10/2026 Corrections Issued JACK KARGODORIAN
Shower Pan 3/10/2026 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 3/18/2026 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 5/15/2026 Partial Approval JOHN KIDWELL