1637 N MCDONALD AVE 90744

Certificate Information: 1637 N MCDONALD AVE 90744

Application / Permit
22010-10000-05756
Plan Check / Job No.
B22LA23869
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
eplan (N) DETACHED GARAGE
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 3/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/29/2022 JOSEPH RAFOLS
Corrections Issued 11/30/2022 JOSEPH RAFOLS
Applicant returned to address corrections 3/15/2023 PINANK PATEL
Applicant returned to address corrections 4/18/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 4/24/2023 FARSHAD ALIMOHAMADI
No Progress 7/13/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 7/13/2023 FARSHAD ALIMOHAMADI
No Progress 7/13/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 7/13/2023 FARSHAD ALIMOHAMADI
No Progress 7/13/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 7/13/2023 FARSHAD ALIMOHAMADI
Issued 7/26/2023 APPLICANT
CofO in Progress 3/13/2024 EUGENE CASSIDY
Permit Finaled 3/13/2024 ANSON MAGLASANG
CofO Issued 3/13/2024 ANSON MAGLASANG
Permit Finaled 3/13/2024 ANSON MAGLASANG

Permit Application Clearance Information

Clean Up Green Up Cleared 12/7/2022 MAXFIELD VERMY
ZA Case Cleared 12/7/2022 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 3/14/2023 KHAING AYE
Roof/Waste drainage to street Cleared 3/15/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2023 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 9/26/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 9/26/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 9/26/2023 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 10/17/2023 Partial Approval EUGENE CASSIDY
METHANE-Barrier 10/17/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 10/17/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/23/2023 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/24/2023 Approved EUGENE CASSIDY
METHANE-Barrier 10/24/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/14/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 11/14/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/20/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 11/20/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 11/27/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/27/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/27/2023 Approved EUGENE CASSIDY
METHANE-Rough 11/27/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 11/27/2023 Approved EUGENE CASSIDY
Drywall Nailing 11/29/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/29/2023 Approved EUGENE CASSIDY
Final 2/16/2024 OK to Issue CofO EUGENE CASSIDY
Footing/Foundation/Slab 2/16/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 2/16/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 2/16/2024 Approved EUGENE CASSIDY
Smoke Detectors 2/16/2024 Approved EUGENE CASSIDY