605 W 101ST ST 90044
Certificate Information: 605 W 101ST ST 90044
- Application / Permit
- 22010-10000-05755
- Plan Check / Job No.
- B22LA23868
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW DETACHED ADU ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Current Status
- Issued on 8/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | SUNMIN LEE |
| Corrections Issued | 12/5/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 8/15/2023 | KHUONG TRUONG |
| Plan Check Approved | 8/18/2023 | KHUONG TRUONG |
| Issued | 8/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 12/22/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 6/26/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/23/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 10/2/2023 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 10/2/2023 | Approved | JOHN KLARIN |
| Sewer | 10/6/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 10/11/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 10/16/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 10/19/2023 | Approved | JOHN KLARIN |
| Special/Order Compliance | 10/19/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 11/9/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 11/9/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 11/9/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/9/2023 | Approved | JOHN KLARIN |
| Insulation | 11/16/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/16/2023 | Approved | JOHN KLARIN |
| Shower Pan | 11/16/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/20/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/4/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 4/4/2024 | Approved | JAMES CHAVEZ |
| Final | 4/4/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 4/4/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 4/4/2024 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 4/4/2024 | Not Required | JAMES CHAVEZ |
| Smoke Detectors | 4/4/2024 | Approved | JAMES CHAVEZ |
| Final | 3/20/2026 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 3/20/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/20/2026 | Approved | ARTHUR NEGRETE |