6213 S RIMPAU BLVD 90043

Certificate Information: 6213 S RIMPAU BLVD 90043

Application / Permit
22010-10000-05739
Plan Check / Job No.
B22LA23811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PARTIAL DEMOLITION OF (E) GARAGE TO CONVERT TO ADU WITH 2ND STORY ADDITION PER ORDINANCE.
Permit Issued
Issued on 1/31/2024
Issuing Office
Current Status
CofO Issued on 12/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/4/2023 FARSHAD ALIMOHAMADI
Corrections Issued 1/6/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 1/10/2023 PRANITA SHAH
Applicant returned to address corrections 12/7/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/10/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/18/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/22/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/24/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 12/28/2023 FARSHAD ALIMOHAMADI
No Progress 1/31/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 1/31/2024 FARSHAD ALIMOHAMADI
Issued 1/31/2024 APPLICANT
CofO in Progress 12/20/2025 SALVADOR MARTINEZ
Permit Finaled 12/21/2025 DEROLD HAUFF
CofO Issued 12/21/2025 DEROLD HAUFF
Permit Finaled 12/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2023 ADRIAN SANCHEZ
Low Impact Development Cleared 8/7/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 8/9/2023 ERIK BEASLEY
Construction near power lines Cleared 9/27/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 11/2/2023 JILVER MAZARIEGOS
Sewer availability Cleared 11/2/2023 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 2/12/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 2/12/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 2/14/2025 Approved MICHAEL LEWIS
HVAC-Rough 2/14/2025 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 2/20/2025 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 2/25/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 2/25/2025 Approved JOSE MACIAS
PLUMBING-Rough 2/25/2025 Approved JOSE MACIAS
Insulation 2/28/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 2/28/2025 Partial Approval ANTHONY RAMOS
Drywall Nailing 3/5/2025 Approved ANTHONY RAMOS
Final 7/21/2025 Not Ready for Inspection WAYNE REGESTER
Footing/Foundation/Slab 7/21/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Approved WAYNE REGESTER
Smoke Detectors 7/21/2025 Corrections Issued WAYNE REGESTER
Final 10/16/2025 Corrections Issued SALVADOR MARTINEZ
Smoke Detectors 10/16/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 12/4/2025 Corrections Issued SALVADOR MARTINEZ
Smoke Detectors 12/4/2025 Corrections Issued SALVADOR MARTINEZ
Final 12/15/2025 Corrections Issued SALVADOR MARTINEZ
Smoke Detectors 12/15/2025 Approved SALVADOR MARTINEZ
Final 12/19/2025 OK to Issue CofO SALVADOR MARTINEZ