11411 W BRADDOCK DR 90230
Certificate Information: 11411 W BRADDOCK DR 90230
- Application / Permit
- 22010-10000-05737
- Plan Check / Job No.
- B22LA23804
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (1/2) NEW DETACHED 1 STORY ADU AT REAR OF PROPERTY CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/29/2022 | APPLICANT |
Assigned to Plan Check Engineer | 12/29/2022 | JAD BASMA |
Corrections Issued | 1/4/2023 | JAD BASMA |
Quality Review Completed | 1/13/2023 | TEODORO DIAZ RODRIGUEZ |
Applicant returned to address corrections | 3/11/2023 | JAD BASMA |
Plan Check Approved | 7/13/2023 | JAD BASMA |
Issued | 7/13/2023 | APPLICANT |
CofO in Progress | 8/5/2024 | JESUS RODRIGUEZ |
Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
CofO Issued | 8/6/2024 | DANIEL ORRANTE |
Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
Address approval | Cleared | 3/10/2023 | JASON NG |
Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | JASON NG |
Sewer availability | Cleared | 3/21/2023 | JASON NG |
Roof/Waste drainage to street | Cleared | 4/4/2023 | JASON NG |
Specific Plan | Cleared | 5/25/2023 | JOSHUA JONES |
Contact Information
Contractor | ; Lic. No.: 957698-B | , |
Inspector Information
WILBER ROSALES, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 7/18/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | RICHARD STEINBACH |
Footing/Foundation/Slab | 9/12/2023 | Approved | RICHARD STEINBACH |
Sewer | 9/20/2023 | Partial Approval | HERBERT GIRON |
PLUMBING-Rough | 10/6/2023 | Partial Approval | JESUS RODRIGUEZ |
Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Approved | JESUS RODRIGUEZ |
PLUMBING-Rough | 12/1/2023 | Approved | JESUS RODRIGUEZ |
Sewer | 12/1/2023 | Approved | JESUS RODRIGUEZ |
Verify Sprinkler Sign Off | 12/1/2023 | Approved | JESUS RODRIGUEZ |
BUILDING-Rough-Frame | 12/15/2023 | Approved | JESUS RODRIGUEZ |
ELECTRICAL-Rough | 12/15/2023 | Approved | JESUS RODRIGUEZ |
Green Building Rough | 12/15/2023 | Approved | JESUS RODRIGUEZ |
HVAC-Rough | 12/15/2023 | Approved | JESUS RODRIGUEZ |
Interior/Exterior Lathing | 12/15/2023 | Approved | JESUS RODRIGUEZ |
MERV13>=Rough | 12/15/2023 | Approved | JESUS RODRIGUEZ |
Verify Sprinkler Sign Off | 12/15/2023 | Approved | JESUS RODRIGUEZ |
Insulation | 1/25/2024 | Conditional Approval | JESUS RODRIGUEZ |
Drywall Nailing | 2/1/2024 | Approved | JESUS RODRIGUEZ |
Insulation | 2/1/2024 | Approved | JESUS RODRIGUEZ |
Interior/Exterior Lathing | 2/12/2024 | Approved | BOBBY KEY |
Underground Mechanical | 5/10/2024 | Approved | JESUS RODRIGUEZ |
ELECTRICAL-Final | 5/15/2024 | Corrections Issued | JESUS RODRIGUEZ |
HVAC-Final | 5/15/2024 | Corrections Issued | JESUS RODRIGUEZ |
PLUMBING-Final | 5/15/2024 | Corrections Issued | JESUS RODRIGUEZ |
ELECTRICAL-Final | 6/12/2024 | Approved | JESUS RODRIGUEZ |
HVAC-Final | 6/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
Final | 8/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
HVAC-Final | 8/1/2024 | Approved | JESUS RODRIGUEZ |
MERV13>=Final | 8/1/2024 | Approved | JESUS RODRIGUEZ |
SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Required | JESUS RODRIGUEZ |
Service/Power Release | 8/1/2024 | Approved | JESUS RODRIGUEZ |
Smoke Detectors | 8/1/2024 | Approved | JESUS RODRIGUEZ |
Final | 8/2/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
PLUMBING-Final | 8/2/2024 | Approved | JESUS RODRIGUEZ |