4248 1/2 E YORK BLVD 90065

Certificate Information: 4248 1/2 E YORK BLVD 90065

Application / Permit
22010-10000-05733
Plan Check / Job No.
B22LA23796
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW ONE STORY ADU PER LAMC 12.22 A.33 (c) AND (d). ALL WORK PER WFPP
Permit Issued
Issued on 9/1/2023
Issuing Office
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 DANIEL SANJUAN
Corrections Issued 12/2/2022 DANIEL SANJUAN
Applicant returned to address corrections 8/24/2023 DANIEL SMILEY
Applicant returned to address corrections 8/29/2023 ARSALAN SHABESTARI
Plan Check Approved 8/31/2023 ARSALAN SHABESTARI
Issued 9/1/2023 APPLICANT
CofO in Progress 2/19/2025 CRAIG DAVIS
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/17/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/17/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 1/20/2023 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 1/23/2023 TREVOR QUAN
Sewer availability Cleared 1/23/2023 TREVOR QUAN
Supp. Use District POD/CDO/TDO Cleared 8/14/2023 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2023 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/24/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 10/24/2023 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 11/6/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/13/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 12/13/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/2/2024 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/2/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/2/2024 Approved HAMIK HARTOUNIAN
Insulation 1/16/2024 Corrections Issued HAMIK HARTOUNIAN
Insulation 1/23/2024 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 4/10/2024 Approved ROY SPAULDING
Shower Pan 4/10/2024 Approved ROY SPAULDING
Underground Mechanical 10/4/2024 Partial Approval THOMAS LOGRASSO
Final 1/14/2025 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/14/2025 Approved THOMAS LOGRASSO
Smoke Detectors 1/14/2025 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/18/2025 Approved CRAIG DAVIS
ELECTRICAL-Final 2/18/2025 Approved CRAIG DAVIS
Final 2/18/2025 OK to Issue CofO CRAIG DAVIS
HVAC-Final 2/18/2025 Approved CRAIG DAVIS
PLUMBING-Final 2/18/2025 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved CRAIG DAVIS
Service/Power Release 2/18/2025 Approved CRAIG DAVIS