3216 S SHASTA CIR SOUT 90065
Certificate Information: 3216 S SHASTA CIR SOUT 90065
- Application / Permit
- 22010-10000-05731
- Plan Check / Job No.
- B22LA23790
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: DETACHED ADU USING FACTORY BUILT HOUSING PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 7/12/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | VARAND SARKISIAN |
| Corrections Issued | 12/27/2022 | VARAND SARKISIAN |
| Quality Review Completed | 1/5/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/10/2023 | VARAND SARKISIAN |
| Applicant returned to address corrections | 2/16/2023 | VARAND SARKISIAN |
| Applicant returned to address corrections | 3/6/2023 | VARAND SARKISIAN |
| Plan Check Approved | 7/12/2023 | VARAND SARKISIAN |
| Issued | 7/12/2023 | APPLICANT |
| CofO in Progress | 12/20/2024 | ROY SPAULDING |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/22/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2023 | WALLIE JONG |
| Sewer availability | Cleared | 3/24/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/12/2023 | KURT CORRAL |
| Miscellaneous | Cleared | 4/12/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 5/26/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | JEANIE LAM |
| Supp. Use District POD/CDO/TDO | Cleared | 6/21/2023 | NICOLE SANCHEZ |
| ZI | Cleared | 6/21/2023 | NICOLE SANCHEZ |
| GPI Written Notices | Cleared | 7/10/2023 | ANDREW SANTIAGO |
| Grading Pre-Inspection | Cleared | 7/10/2023 | VARAND SARKISIAN |
Contact Information
| Contractor | U S Modular Inc; Lic. No.: 943047-B | , |
| Engineer | Anis,, Mohsen; Lic. No.: C69482 | 2190 WEMBLEY LN CORONA, CA 92881 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/11/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/11/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/11/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/11/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/11/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/16/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/23/2024 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 4/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/14/2024 | Approved | CRAIG VAUGHAN |
| Gas Test | 6/14/2024 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/14/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/21/2024 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/25/2024 | Partial Approval | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 6/25/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 7/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 7/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 7/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 7/31/2024 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 10/4/2024 | No Access for Inspection | ROY SPAULDING |
| Gas Test | 10/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/27/2024 | Approved | ROY SPAULDING |
| Final | 11/27/2024 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 11/27/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 11/27/2024 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 11/27/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 11/27/2024 | Approved | ROY SPAULDING |
| Final | 12/6/2024 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 12/9/2024 | Not Ready for Inspection | ROY SPAULDING |
| Final | 12/11/2024 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 12/11/2024 | Approved | ROY SPAULDING |