2657 N LARMAR ROAD 90068

Certificate Information: 2657 N LARMAR ROAD 90068

Application / Permit
22010-10000-05708
Plan Check / Job No.
B22LA23657
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
CONSTRUCTION OF A CANTILEVERING PATIO COVER(STEEL STRUCTURE) 20'-2" (W) x 13' 4-3/8" (D) x 9'-9"
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 CARLOS MONTES
Corrections Issued 12/6/2022 CARLOS MONTES
Quality Review Completed 1/6/2023 KEN GILL
Building Plans Picked Up 1/11/2023 APPLICANT
Plan Check Approved 2/28/2023 CARLOS MONTES
Issued 2/28/2023 APPLICANT
CofO in Progress 9/25/2025 BRIAN SULLIVAN
Permit Finaled 9/26/2025 DEROLD HAUFF
CofO Issued 9/26/2025 DEROLD HAUFF
Permit Finaled 9/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/19/2023 OLGA AYALA
ZI Cleared 1/19/2023 OLGA AYALA
BHO/Hillside ordinance Cleared 1/20/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/20/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/20/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/20/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/20/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/20/2023 AMAAN MALIK
Grading Pre-Inspection Cleared 1/20/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 1/20/2023 AMAAN MALIK
Distance to fire station Cleared 2/28/2023 JOHN CONNEALLY
Hydrant and Access approval Cleared 2/28/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/19/2025 Approved BRIAN SULLIVAN
Final 9/19/2025 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 9/19/2025 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 9/19/2025 Approved BRIAN SULLIVAN
Smoke Detectors 9/19/2025 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/19/2025 Approved BRIAN SULLIVAN
Final 9/24/2025 OK to Issue CofO BRIAN SULLIVAN