2249 N CAZADOR DR 90065

Certificate Information: 2249 N CAZADOR DR 90065

Application / Permit
22010-10000-05683
Plan Check / Job No.
B22LA23563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story residence with attached garage AT REAR OF LOT
Permit Issued
Issued on 8/14/2023
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2022 APPLICANT
Assigned to Plan Check Engineer 12/23/2022 JOE VO
Corrections Issued 12/25/2022 JOE VO
Quality Review Completed 1/4/2023 GARO TELMI
Applicant returned to address corrections 5/11/2023 JOE VO
Applicant returned to address corrections 6/27/2023 JOE VO
Plan Check Approved 8/7/2023 JOE VO
Issued 8/14/2023 APPLICANT
CofO in Progress 2/22/2025 THOMAS LOGRASSO
No Progress 2/22/2025 THOMAS LOGRASSO
CofO in Progress 2/22/2025 THOMAS LOGRASSO
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/26/2022 JOE VO
Address approval Cleared 1/12/2023 CELINA MORENO
Permit Cleared 1/12/2023 CELINA MORENO
Disturb/Remove Protected Trees Cleared 1/18/2023 ADALBERTO VERA
BHO/Hillside ordinance Cleared 1/19/2023 CELINA MORENO
BHO/Hillside ordinance Cleared 1/19/2023 CELINA MORENO
BHO/Hillside ordinance Cleared 1/19/2023 CELINA MORENO
BHO/Hillside ordinance Cleared 1/19/2023 CELINA MORENO
BHO/Hillside ordinance Cleared 1/19/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/20/2023 CELINA MORENO
Sewer availability Cleared 1/20/2023 CELINA MORENO
Hydrant and Access approval Cleared 2/4/2023 KURT CORRAL
Landscape for retaining wall Cleared 6/27/2023 MAXFIELD VERMY
Specific Plan Cleared 6/27/2023 MAXFIELD VERMY
Low Impact Development Cleared 7/31/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/1/2023 CHRISTINA BRACO

Contact Information

Architect Karabachian,, Sevak A; Lic. No.: NA38632       ,
Contractor Green Eco Construction Inc; Lic. No.: 1063673-B       ,
Engineer Arakelyan,, Aram; Lic. No.: NA82796       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/22/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 9/22/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 9/27/2023 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 9/28/2023 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/4/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/5/2023 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 10/23/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/24/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/30/2023 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 11/2/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/14/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 11/15/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 11/21/2023 Conditional Approval BRENDAN MORELLI
Wood Frame 12/7/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/8/2023 Corrections Issued HAMIK HARTOUNIAN
Deputy Reinf. Concrete 12/18/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/19/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Reinf. Concrete 12/27/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/16/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/24/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/25/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 1/25/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/3/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 4/3/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/10/2024 Approved BRIAN SULLIVAN
HVAC-Rough 4/10/2024 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 4/10/2024 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/16/2024 Approved BRIAN SULLIVAN
Green Building Rough 4/16/2024 Approved BRIAN SULLIVAN
HVAC-Rough 4/16/2024 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/16/2024 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/16/2024 Approved BRIAN SULLIVAN
Insulation 4/26/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 5/8/2024 Partial Approval THOMAS LOGRASSO
Sewer 5/13/2024 Partial Approval THOMAS LOGRASSO
Pre-Inspection 5/28/2024 Partial Inspection THOMAS LOGRASSO
Shower Pan 6/7/2024 Partial Approval LILIANA PORTILLO
Underground Mechanical 6/14/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 6/21/2024 Not Ready for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 6/21/2024 Approved BRENDAN MORELLI
Shower Pan 6/21/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 6/25/2024 Partial Inspection BRIAN SULLIVAN
Sewer 6/28/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 6/28/2024 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 7/5/2024 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 7/12/2024 Partial Inspection THOMAS LOGRASSO
Drywall Nailing 7/26/2024 Partial Approval THOMAS LOGRASSO
Shower Pan 7/26/2024 Approved THOMAS LOGRASSO
Drywall Nailing 8/6/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/6/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/6/2024 Partial Approval THOMAS LOGRASSO
Service/Power Release 8/8/2024 Approved CRAIG VAUGHAN
Gas Test 10/25/2024 Approved THOMAS LOGRASSO
Final 11/13/2024 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/13/2024 Approved THOMAS LOGRASSO
Final 2/18/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/18/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 2/18/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/18/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/18/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/21/2025 Approved THOMAS LOGRASSO
Final 2/21/2025 OK to Issue CofO THOMAS LOGRASSO
Footing/Foundation/Slab 2/21/2025 Approved THOMAS LOGRASSO