7524 S HOOVER ST 90044

Certificate Information: 7524 S HOOVER ST 90044

Application / Permit
22010-10000-05647
Plan Check / Job No.
B22LA23410
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 5 story, Type IIIA, 79 unit apartment building- 100% affordable (62 low income & 16 moderate income house holds and 1 manger's unit)
Permit Issued
Issued on 9/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 KESETE HAREGOT
Corrections Issued 12/20/2022 KESETE HAREGOT
Quality Review Completed 12/27/2022 RODOLFO ARIAS
Plan Check Approved 6/21/2023 KESETE HAREGOT
Issued 9/11/2023 APPLICANT
TCO Issued (Expire Date: 03-02-2026) 9/3/2025 ERNESTO CORRAL
CofO in Progress 9/24/2025 JAMES POWERS
Permit Finaled 9/24/2025 ERNESTO CORRAL
CofO Issued 9/24/2025 ERNESTO CORRAL
Permit Finaled 9/24/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/9/2023 CELINA MORENO
Bicycle Parking Cleared 2/1/2023 JEREMY CHOK
Address approval Cleared 2/3/2023 CELINA MORENO
Hydrant and Access approval Cleared 2/10/2023 LAVEON RIDER
Trees in Parkway Cleared 3/7/2023 ADALBERTO VERA
Low Impact Development Cleared 3/20/2023 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/23/2023 CELINA MORENO
Sewer availability Cleared 3/29/2023 CELINA MORENO
Construction near power lines Cleared 4/13/2023 RIDWAN HARDY
Fire Marshal Fire Life Safety Cleared 4/13/2023 MENOA AGHAJANI
Permit Cleared 4/13/2023 CELINA MORENO
Building over 36-ft Cleared 4/24/2023 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/24/2023 CALOSHA APPROVED
Highway dedication Cleared 4/25/2023 CELINA MORENO
Green Code Cleared 4/27/2023 KESETE HAREGOT
DAS Clearance Cleared 5/3/2023 KESETE HAREGOT
DCP conditions approval Cleared 5/30/2023 LOUIE MILLER
Density Bonus Cleared 5/30/2023 LOUIE MILLER
SB8 RUD Cleared 5/30/2023 LOUIE MILLER
"Q" conditions Cleared 6/5/2023 DALIA MOKAYED
Frnt yard landscape/Water mgmt Cleared 6/5/2023 DALIA MOKAYED
Opn space landscape/Water mgmt Cleared 6/5/2023 DALIA MOKAYED
Site Plan review Cleared 6/5/2023 DALIA MOKAYED

Contact Information

Architect , ; Lic. No.: C38560 3360 VICKERS DR.      GLENDALE, CA 91208
Contractor Steiner Douglas Construction Inc; Lic. No.: 916002-B       ,
Engineer Hovaguimian,, George Vahe; Lic. No.: M22114 11517 BURBANK BLVD      NORTH HOLLYWOOD, CA 91601
Engineer Oganesyan,, Sarkis; Lic. No.: C76665 1025 N. HOWARD ST      GLENDALE, CA 91207
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect Gagne,, Paul Elliott; Lic. No.: LA6223 6620 MURIETTA AVE      VAN NUYS, CA 91405

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/13/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/21/2023 Partial Approval JAMES POWERS
Pre-Inspection 12/21/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 12/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/27/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/27/2023 Partial Approval JAMES POWERS
Pre-Inspection 12/27/2023 Partial Approval JAMES POWERS
Structural Steel Frame 12/27/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/29/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/3/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 1/31/2024 Partial Approval JAMES POWERS
Wood Frame 1/31/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 3/7/2024 Partial Approval JAMES POWERS
Wood Frame 3/8/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 3/12/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 3/19/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/22/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 3/22/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/22/2024 Partial Approval JAMES POWERS
Wood Frame 3/22/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 3/27/2024 Partial Approval JAMES POWERS
Wood Frame 3/29/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 4/24/2024 Partial Approval JAMES POWERS
Wood Frame 4/25/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval JAMES POWERS
Wood Frame 5/31/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/1/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 7/1/2024 No Access for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/2/2024 Partial Approval JAMES POWERS
Insulation 8/14/2024 Partial Approval JAMES POWERS
Wood Frame 8/14/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/19/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval JAMES POWERS
Insulation 8/19/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Order to Comply Issued JAMES POWERS
Insulation 8/20/2024 Not Ready for Inspection JAMES POWERS
Insulation 8/21/2024 Partial Approval JAMES POWERS
Wood Frame 8/21/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/23/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/28/2024 Partial Approval JAMES POWERS
Insulation 8/28/2024 Not Ready for Inspection JAMES POWERS
Structural Steel Frame 8/28/2024 Approved JAMES POWERS
Wood Frame 8/28/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/4/2024 Partial Approval JAMES POWERS
Insulation 9/4/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 9/4/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/13/2024 Order to Comply Issued JAMES POWERS
Wood Frame 9/13/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/26/2024 Partial Approval JAMES POWERS
Insulation 9/26/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 9/26/2024 Partial Inspection JAMES POWERS
Drywall Nailing 10/25/2024 Not Ready for Inspection LARRY ARNICK
Insulation 10/25/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 10/25/2024 Partial Approval LARRY ARNICK
Drywall Nailing 11/5/2024 Not Ready for Inspection JAMES POWERS
Insulation 11/5/2024 Not Ready for Inspection JAMES POWERS
Insulation 11/13/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 11/13/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 11/15/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/12/2024 Partial Approval JAMES POWERS
Insulation 12/12/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 12/19/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/26/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/28/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 3/13/2025 Partial Approval LARRY ARNICK
Drywall Nailing 4/4/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/4/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/11/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/15/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/17/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/29/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/7/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/16/2025 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 5/16/2025 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/19/2025 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/19/2025 Partial Approval JAMES POWERS
Pre-Inspection 7/8/2025 Partial Approval JAMES POWERS
Final 7/16/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/16/2025 Approved JAMES POWERS
Green Building Final 7/16/2025 Approved JAMES POWERS
Green Building Rough 7/16/2025 Approved JAMES POWERS
Reinforced Masonry Frame 7/16/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready JAMES POWERS
Smoke Detectors 7/16/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/16/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Not Ready JAMES POWERS
Final 8/8/2025 OK for TCO JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved JAMES POWERS
Final 8/15/2025 Partial Approval JAMES POWERS
Final 9/10/2025 OK for TCO JAMES POWERS
Final 9/24/2025 OK to Issue CofO JAMES POWERS