2053 W 85TH ST 90047
Certificate Information: 2053 W 85TH ST 90047
- Application / Permit
- 22010-10000-05645
- Plan Check / Job No.
- B22LA23397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE AND ADDITION TO NEW ADU (700.5 SF) PER LAMC ORDINANCE
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2023 | ADAM HEGAZI |
| Corrections Issued | 1/10/2023 | ADAM HEGAZI |
| Applicant returned to address corrections | 8/14/2024 | DANIEL SANJUAN |
| Applicant returned to address corrections | 8/20/2024 | LUKE GONZALES |
| Plan Check Approved | 8/21/2024 | LUKE GONZALES |
| Issued | 8/23/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/3/2023 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 5/20/2024 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/8/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/9/2024 | DAVID VO |
Contact Information
| Contractor | Xi Developments; Lic. No.: 1115857-B | 5875 GREEN VALLEY CIRCLE CULVER CITY, CA 90230 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 8/29/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 9/3/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/20/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 1/13/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 1/13/2025 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 1/13/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/20/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 2/20/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/20/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 2/20/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Green Building Rough | 2/25/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Wood Frame | 2/25/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 2/28/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 2/28/2025 | Approved | JOSE MACIAS |
| Insulation | 4/24/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 5/6/2025 | Approved | WAYNE REGESTER |