4437 N CALHOUN AVE 91423
Certificate Information: 4437 N CALHOUN AVE 91423
- Application / Permit
- 22010-10000-05640
- Plan Check / Job No.
- B22LA23366
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan (N) 2-STORY SFD WITH ATTACHED GARAGE 1 OF 3
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | ADRIANA LOPEZ |
| Corrections Issued | 1/5/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 1/25/2023 | CHAD DOI |
| Applicant returned to address corrections | 5/31/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 6/15/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/27/2023 | ADRIANA LOPEZ |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 9/22/2025 | MISAEL ESPARZA |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 2/7/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/13/2023 | KURT CORRAL |
| ZI | Cleared | 3/30/2023 | JAZMIN ROQUE |
| Low Impact Development | Cleared | 4/25/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/25/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/16/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 3/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 5/1/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/9/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/15/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/10/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 9/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 9/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/30/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/21/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/21/2024 | Partial Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 10/21/2024 | Approved | MISAEL ESPARZA |
| Insulation | 10/25/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/5/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/13/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/20/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 5/20/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/28/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/9/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 7/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 7/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 9/19/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 9/19/2025 | Approved | MISAEL ESPARZA |