3547-3547 1/2 E 3RD ST 90063

Certificate Information: 3547-3547 1/2 E 3RD ST 90063

Application / Permit
22010-10000-05626
Plan Check / Job No.
B22LA23321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New irr. shape 22'x23'9" attached ADU per engineer details per LAMC 12.22 A.33 (c) and (e)). "COMPLY WITH DEPARTMENT ORDER effective date 05/13/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 953993.
Permit Issued
Issued on 2/3/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 AUNG SOE
Corrections Issued 11/30/2022 AUNG SOE
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 1/24/2023 CRISTINA SALAZAR
Plan Check Approved 1/26/2023 CRISTINA SALAZAR
Issued 2/3/2023 APPLICANT
CofO in Progress 11/5/2024 PEDRO SIERRA
Permit Finaled 5/14/2025 DANIEL SANCHEZ
CofO Issued 5/14/2025 DANIEL SANCHEZ
Permit Finaled 5/14/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 1/5/2023 STEVE MELGAR
Roof/Waste drainage to street Cleared 1/5/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/9/2023 STEVE MELGAR
Grading Pre-Inspection Cleared 1/9/2023 KIRK LINKLATER
Sewer availability Cleared 1/9/2023 STEVE MELGAR
Tenant Habitability Plan Cleared 1/12/2023 ISMAEL HERNANDEZ
Clean Up Green Up Cleared 1/18/2023 ANACANY HURTADO
ZA Case Cleared 1/18/2023 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2023 Approved PEDRO SIERRA
BUILDING-Rough-Frame 11/30/2023 Partial Approval PEDRO SIERRA
Green Building Rough 11/30/2023 Not Ready for Inspection PEDRO SIERRA
MERV13>=Rough 11/30/2023 Not Ready for Inspection PEDRO SIERRA
ELECTRICAL-Rough 1/25/2024 Approved PEDRO SIERRA
PLUMBING-Rough 3/1/2024 Approved PEDRO SIERRA
Shower Pan 3/21/2024 Corrections Issued DANIEL DELACRUZ
Interior/Exterior Lathing 3/26/2024 Approved DANIEL DELACRUZ
Shower Pan 3/26/2024 Approved DANIEL DELACRUZ
Smoke Detectors 5/8/2024 Not Ready for Inspection PEDRO SIERRA
BUILDING-Rough-Frame 7/12/2024 Approved PEDRO SIERRA
ELECTRICAL-Final 7/12/2024 Conditional Approval PEDRO SIERRA
Final 7/12/2024 Not Ready for Inspection PEDRO SIERRA
Green Building Final 7/12/2024 Not Ready for Inspection PEDRO SIERRA
Green Building Rough 7/12/2024 Approved PEDRO SIERRA
HVAC-Rough 7/12/2024 Approved PEDRO SIERRA
MERV13>=Final 7/12/2024 Not Ready for Inspection PEDRO SIERRA
MERV13>=Rough 7/12/2024 Approved PEDRO SIERRA
PLUMBING-Final 7/12/2024 Corrections Issued PEDRO SIERRA
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Not Ready PEDRO SIERRA
Smoke Detectors 7/12/2024 Not Ready for Inspection PEDRO SIERRA
PLUMBING-Final 8/2/2024 Approved PEDRO SIERRA
Smoke Detectors 8/2/2024 Approved PEDRO SIERRA
ELECTRICAL-Final 8/9/2024 Not Ready for Inspection PEDRO SIERRA
MERV13>=Final 8/9/2024 Approved PEDRO SIERRA
Final 9/27/2024 OK to Issue CofO PEDRO SIERRA
Green Building Final 9/27/2024 Approved PEDRO SIERRA
PLUMBING-Final 9/27/2024 Approved PEDRO SIERRA
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved PEDRO SIERRA