2420 S OCEAN AVE 90291

Certificate Information: 2420 S OCEAN AVE 90291

Application / Permit
22010-10000-05584
Plan Check / Job No.
B22LA23154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] NEW 2-STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 8/21/2025
Issuing Office
Metro
Current Status
Issued on 8/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/16/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 MAHNAZ NOURHASHEMI
Corrections Issued 12/17/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 1/6/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 6/10/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 6/27/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/15/2025 MAHNAZ NOURHASHEMI
Issued 8/21/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 12/28/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 1/11/2023 CATHERINE ADROVER
Hydrant and Access approval Cleared 1/22/2023 MATTHEW CRAIG
Specific Plan Cleared 2/14/2023 PEDRO AYALA
Specific Plan Cleared 2/14/2023 PEDRO AYALA
Flood clearance Cleared 6/22/2023 MIGUEL RODRIGUEZ
Low Impact Development Cleared 6/27/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 6/30/2023 JASON NG
Coastal Zone Cleared 5/14/2024 BRENNEN OBETO
Frnt yard landscape/Water mgmt Cleared 5/14/2024 BRENNEN OBETO
ZI Cleared 5/14/2024 BRENNEN OBETO
ZI Cleared 5/14/2024 BRENNEN OBETO
Hold Cleared 10/1/2025 MARIA VENDIVIL

Contact Information

Contractor Vip Builders Inc; Lic. No.: 1110117-B 3968 E CESAR E CHAVEZ AVE      LOS ANGELES, CA 90063
Engineer Chandler,, Tyler Benjamin; Lic. No.: C91617 5348 VIA SAN DELARRO ST 1      LOS ANGELES, CA 90022

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2025 Not Ready for Inspection RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 12/12/2025 Partial Approval RUBEN RIVAS
Deputy Steel/Welding 12/29/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 1/22/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Approved RUBEN RIVAS
ELECTRICAL-Rough 4/21/2026 Corrections Issued RUBEN RIVAS
HVAC-Rough 4/21/2026 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 4/21/2026 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 5/15/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 5/15/2026 Corrections Issued RUBEN RIVAS
Green Building Rough 5/15/2026 Approved RUBEN RIVAS
HVAC-Rough 5/15/2026 Approved RUBEN RIVAS
PLUMBING-Rough 5/15/2026 Approved RUBEN RIVAS
Insulation 5/20/2026 Corrections Issued RUBEN RIVAS
Insulation 5/28/2026 Approved RUBEN RIVAS
Drywall Nailing 6/3/2026 Approved RUBEN RIVAS