10551 N SHARP AVE 91331
Certificate Information: 10551 N SHARP AVE 91331
- Application / Permit
- 22010-10000-05578
- Plan Check / Job No.
- B22LA23123
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU per Ordinance
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/11/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/22/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 11/29/2022 | APPLICANT |
| Plan Check Approved | 1/6/2023 | VICTOR CHEN |
| Issued | 1/11/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/3/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/9/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/9/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/17/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 6/12/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 6/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/11/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/11/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 11/20/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/20/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/7/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/7/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/7/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/12/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 12/22/2023 | Corrections Issued | MATTHEW NELSON |
| Insulation | 12/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 1/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/3/2024 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 1/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/24/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/27/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/14/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 5/14/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 5/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/28/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | JENNIFER RABUCHIN |
| Final | 1/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/3/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 1/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/3/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 1/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 10/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 10/8/2025 | Approved | JENNIFER RABUCHIN |