10242 W MONTE MAR DR 90064

Certificate Information: 10242 W MONTE MAR DR 90064

Application / Permit
22010-10000-05563
Plan Check / Job No.
B22LA23018
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD, 2-story (irregular shape 54'3" x 57'7", 3442 SQFT) residence w/ attached garage, basement, elevator, and roof deck
Permit Issued
Issued on 5/9/2023
Issuing Office
Current Status
CofO Issued on 2/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 NGHI SU
Corrections Issued 11/19/2022 NGHI SU
Quality Review Completed 12/2/2022 KEN GILL
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 3/28/2023 NGHI SU
Plan Check Approved 5/4/2023 NGHI SU
Issued 5/9/2023 APPLICANT
CofO in Progress 2/25/2025 ARAM AVEDISIAN
CofO Issued 2/28/2025 RICHARD STEINBACH
Permit Finaled 2/28/2025 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/16/2022 KURT CORRAL
Specific Plan Cleared 1/30/2023 PEDRO AYALA
Low Impact Development Cleared 2/10/2023 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 2/17/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 2/17/2023 DINAH GARIN
Sewer availability Cleared 2/17/2023 DINAH GARIN
Excavation more than 5-ft deep Cleared 3/28/2023 CALOSHA APPROVED
GPI Written Notices Cleared 4/12/2023 NGHI SU
Grading Pre-Inspection Cleared 4/12/2023 NGHI SU

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/20/2023 Conditional Approval DAVID FEILER
Piling/Pier/Caisson 6/27/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 8/22/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Barrier 8/22/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 8/22/2023 Not Ready for Inspection CLAYTON GRAHAM
Pre-Inspection 8/28/2023 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 9/25/2023 Partial Approval MEL KHACHATOURIAN
METHANE-Barrier 9/25/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 9/25/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/13/2023 Partial Approval CLAYTON GRAHAM
METHANE-Barrier 10/13/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 10/13/2023 Not Ready for Inspection CLAYTON GRAHAM
Deputy Shotcrete 10/18/2023 Conditional Approval CLAYTON GRAHAM
METHANE-Subgrade 11/2/2023 Approved ARAM AVEDISIAN
Deputy Methane Barrier 11/6/2023 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 11/7/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Methane Barrier 11/8/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/13/2023 Approved OGANES TARAKHCHYAN
METHANE-Barrier 11/13/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 3/7/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/21/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/21/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 3/22/2024 Approved OGANES TARAKHCHYAN
METHANE-Rough 3/22/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/4/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 4/4/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/4/2024 Partial Approval OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 4/4/2024 Approved OGANES TARAKHCHYAN
Insulation 4/10/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/15/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/16/2024 Approved AMY COLIN
Shower Pan 4/16/2024 Approved AMY COLIN
ELECTRICAL-Final 10/4/2024 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 10/4/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 10/10/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 10/25/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 10/25/2024 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 10/25/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 10/29/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 10/29/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 11/4/2024 Approved ASHLEY THOMPSON
HVAC-Final 11/4/2024 Approved ASHLEY THOMPSON
PLUMBING-Final 11/4/2024 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 11/4/2024 Approved ASHLEY THOMPSON
Final 12/18/2024 Corrections Issued KIRK SANDERS
Gas Test 12/18/2024 Approved KIRK SANDERS
Green Building Final 12/18/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 12/18/2024 Not Ready for Inspection KIRK SANDERS
Final 2/3/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 2/3/2025 Approved BOBBY KEY
Final 2/25/2025 OK to Issue CofO ARAM AVEDISIAN