2144 W 75TH ST 90047

Certificate Information: 2144 W 75TH ST 90047

Application / Permit
22010-10000-05554
Plan Check / Job No.
B22LA22995
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per Ordinance with attached 2-car garage
Permit Issued
Issued on 2/16/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2022 APPLICANT
Assigned to Plan Check Engineer 11/18/2022 VICTOR CHEN
Corrections Issued 11/22/2022 VICTOR CHEN
Building Plans Picked Up 12/13/2022 APPLICANT
Issued 2/16/2023 APPLICANT
CofO in Progress 9/27/2023 STUART CHAPMAN
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/10/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/10/2023 AMAAN MALIK
Sewer availability Cleared 1/10/2023 AMAAN MALIK
Construction within easement Cleared 2/4/2023 RIDWAN HARDY
Low Impact Development Cleared 2/10/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/14/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/22/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/28/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 4/4/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 5/17/2023 Approved ENRIQUE MIRELES
Insulation 5/22/2023 Approved ENRIQUE MIRELES
Drywall Nailing 5/30/2023 Approved ENRIQUE MIRELES
Gas Test 6/23/2023 Approved ENRIQUE MIRELES
Service/Power Release 6/29/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/12/2023 Conditional Approval DAVID FEILER
Final 9/12/2023 Corrections Issued DAVID FEILER
Green Building Final 9/12/2023 Approved DAVID FEILER
Green Building Rough 9/12/2023 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved DAVID FEILER
Smoke Detectors 9/12/2023 Approved DAVID FEILER
Verify Sprinkler Sign Off 9/12/2023 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 9/18/2023 Approved STUART CHAPMAN
Final 9/18/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 9/18/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 9/26/2023 Approved STUART CHAPMAN
Final 9/26/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 9/26/2023 Approved STUART CHAPMAN
PLUMBING-Final 9/26/2023 Approved STUART CHAPMAN