5727 N LEMONA AVE 91411
Certificate Information: 5727 N LEMONA AVE 91411
- Application / Permit
- 22010-10000-05529
- Plan Check / Job No.
- B22LA22924
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan DETACHED NEW ADU 1,015 SQ.FT AT REAR OF THE PROPERTY
- Permit Issued
- Issued on 6/3/2023
- Issuing Office
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 11/19/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 11/30/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 3/31/2023 | MARCELA FRANQUEZ |
| Issued | 6/3/2023 | APPLICANT |
| CofO in Progress | 12/18/2023 | RYAN SALAZAR |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
| CofO Issued | 3/21/2024 | RUBEN SALAS |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/9/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/10/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/10/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/18/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Ikon Development Corp; Lic. No.: 1033081-B | , |
| Contractor | Ikon; Lic. No.: 1033081-B | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 7/11/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/2/2023 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/2/2023 | Off-Hour Fees Due | |
| Verify Sprinkler Sign Off | 8/2/2023 | Off-Hour Fees Due | |
| Wood Frame | 8/2/2023 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 8/3/2023 | No Access for Inspection | DAVID MATSON |
| Green Building Rough | 8/3/2023 | No Access for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 8/3/2023 | No Access for Inspection | DAVID MATSON |
| Wood Frame | 8/3/2023 | No Access for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 8/29/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/29/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/29/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Conditional Approval | RYAN SALAZAR |
| Insulation | 9/5/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/11/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/11/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 9/11/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/18/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 9/18/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/28/2023 | Approved | RYAN SALAZAR |
| Sewer | 10/16/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/16/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/16/2023 | Off-Hour Fees Due | |
| Final | 11/16/2023 | Off-Hour Fees Due | |
| Final | 11/16/2023 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 11/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 11/16/2023 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 11/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 11/16/2023 | Off-Hour Fees Due | |
| Smoke Detectors | 11/16/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 11/16/2023 | Off-Hour Fees Due | |
| Verify Sprinkler Sign Off | 11/16/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 11/16/2023 | Off-Hour Fees Due | |
| Final | 12/8/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 12/8/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 12/8/2023 | Approved | RYAN SALAZAR |
| Final | 12/15/2023 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 12/15/2023 | Approved | RYAN SALAZAR |