12868 N NORRIS AVE 91342

Certificate Information: 12868 N NORRIS AVE 91342

Application / Permit
22010-10000-05502
Plan Check / Job No.
B22LA22824
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ADU (1200 SQFT) per LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 2/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 MARCELA FRANQUEZ
Corrections Issued 12/8/2022 MARCELA FRANQUEZ
Quality Review Completed 12/14/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/19/2022 APPLICANT
Plan Check Approved 2/7/2023 MARCELA FRANQUEZ
Issued 2/28/2023 APPLICANT
CofO in Progress 7/16/2024 KEVIN BERBERYAN
CofO Issued 7/25/2024 RUBEN SALAS
Permit Finaled 7/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2023 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/31/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/31/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/1/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/1/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 2/1/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Wong,, Jim C; Lic. No.: C69393 1822 E ROUTE 66, SUITE A, PO BOX 328      GLENDORA, CA 91740

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/3/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 4/10/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval ARAM AVEDISIAN
Sewer 4/25/2023 Approved ARAM AVEDISIAN
Underground Mechanical 5/15/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/24/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 5/24/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/24/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/1/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/1/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Approved ARAM AVEDISIAN
Green Building Rough 6/1/2023 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 6/1/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/1/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 6/7/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 6/7/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/7/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 6/14/2023 Corrections Issued THOMAS FINNILA
Insulation 6/16/2023 Approved DAVID ANDERSON
Insulation 6/16/2023 Off-Hour Fees Due
Drywall Nailing 6/20/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/20/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/25/2023 Conditional Approval KEVIN BERBERYAN
Final 9/25/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/25/2023 Conditional Approval KEVIN BERBERYAN
HVAC-Final 9/25/2023 Conditional Approval KEVIN BERBERYAN
PLUMBING-Final 9/25/2023 Conditional Approval KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/25/2023 Conditional Approval KEVIN BERBERYAN
Final 10/11/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/11/2023 Approved KEVIN BERBERYAN
Smoke Detectors 10/11/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Final 11/7/2023 Conditional Approval KEVIN BERBERYAN
Final 11/7/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 2/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/3/2024 Corrections Issued KEVIN BERBERYAN
Final 7/10/2024 OK to Issue CofO KEVIN BERBERYAN