12868 N NORRIS AVE 91342
Certificate Information: 12868 N NORRIS AVE 91342
- Application / Permit
- 22010-10000-05502
- Plan Check / Job No.
- B22LA22824
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU (1200 SQFT) per LAMC 12.22A.33(c) and (d)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 12/8/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 12/14/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/19/2022 | APPLICANT |
| Plan Check Approved | 2/7/2023 | MARCELA FRANQUEZ |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 7/16/2024 | KEVIN BERBERYAN |
| CofO Issued | 7/25/2024 | RUBEN SALAS |
| Permit Finaled | 7/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2023 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 1/31/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/1/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 2/1/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim C; Lic. No.: C69393 | 1822 E ROUTE 66, SUITE A, PO BOX 328 GLENDORA, CA 91740 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 4/25/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 5/15/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/24/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 5/24/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/24/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/26/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/1/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/1/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 6/1/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/1/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/7/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/7/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/14/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 6/16/2023 | Approved | DAVID ANDERSON |
| Insulation | 6/16/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 6/20/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/20/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| Final | 9/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| HVAC-Final | 9/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| PLUMBING-Final | 9/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| Final | 10/11/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 10/11/2023 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 10/11/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/7/2023 | Conditional Approval | KEVIN BERBERYAN |
| Final | 11/7/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 2/7/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 6/3/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 7/10/2024 | OK to Issue CofO | KEVIN BERBERYAN |