1917 S KELTON AVE 90025
Certificate Information: 1917 S KELTON AVE 90025
- Application / Permit
- 22010-10000-05494
- Plan Check / Job No.
- B22LA22777
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE AND TRELLIS
- Permit Issued
- Issued on 5/3/2023
- Issuing Office
- Current Status
- CofO Corrected on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | VIVIAN LAO |
| Corrections Issued | 11/20/2022 | VIVIAN LAO |
| Quality Review Completed | 11/21/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/7/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 3/14/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 3/24/2023 | VIVIAN LAO |
| Plan Check Approved | 3/29/2023 | VIVIAN LAO |
| Issued | 5/3/2023 | APPLICANT |
| Permit Finaled-Status Void | 11/7/2024 | GUADALUPE TOLEDO |
| Re-Activate Permit | 11/27/2024 | GUADALUPE TOLEDO |
| CofO in Progress | 6/6/2025 | KIRK SANDERS |
| CofO Issued-Status Void | 6/11/2025 | RICHARD STEINBACH |
| Permit Finaled-Status Void | 6/11/2025 | RICHARD STEINBACH |
| Re-Activate Permit | 6/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
| CofO Corrected | 5/19/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/12/2022 | JENSON LEE |
| Address approval | Cleared | 12/28/2022 | JENSON LEE |
| Frnt yard landscape/Water mgmt | Cleared | 1/11/2023 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 1/26/2023 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 1/28/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 1/30/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/30/2023 | JENSON LEE |
| GPI Written Notices | Cleared | 2/7/2023 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 2/7/2023 | VIVIAN LAO |
| Miscellaneous | Cleared | 2/8/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: NA64144 | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Sewer | 9/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| Sewer | 9/19/2023 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/24/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 10/26/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/2/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/2/2023 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/11/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 3/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 3/26/2024 | No Access for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 3/26/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 4/1/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/19/2024 | Partial Approval | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 4/19/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/9/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 5/9/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 5/9/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 5/9/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 5/9/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Rough | 5/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 5/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/20/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 5/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/23/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 5/23/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 5/28/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 5/28/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 5/28/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 6/4/2024 | Approved | KIRK SANDERS |
| Deputy Steel/Welding | 6/5/2024 | Conditional Approval | KIRK SANDERS |
| HVAC-Rough | 6/6/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | KIRK SANDERS |
| Final | 6/11/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 6/11/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 6/11/2024 | Approved | KIRK SANDERS |
| Insulation | 6/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 6/17/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 6/25/2024 | Approved | KIRK SANDERS |
| Shower Pan | 8/13/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 10/17/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 12/3/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 12/16/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 12/16/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 12/16/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/17/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 12/17/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/20/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 12/20/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 12/24/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 12/24/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/3/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 1/6/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 1/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/5/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Not Required | KIRK SANDERS |
| Service/Power Release | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 2/5/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 2/25/2025 | Approved | KIRK SANDERS |
| Final | 2/25/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 2/25/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/25/2025 | Approved | KIRK SANDERS |
| Service/Power Release | 2/27/2025 | Approved | KENNETH NAGLE |
| Final | 5/2/2025 | Partial Approval | STEPHANIE SWANSON |
| Green Building Final | 5/2/2025 | Approved | STEPHANIE SWANSON |
| Final | 6/6/2025 | OK to Issue CofO | KIRK SANDERS |