5200 W CENTURY BLVD 90045
Certificate Information: 5200 W CENTURY BLVD 90045
- Application / Permit
- 22010-10000-05469
- Plan Check / Job No.
- B22LA22710
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Exterior courtyard renovation for new benches and landscaping work.
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 6/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | TU HUA |
| Corrections Issued | 11/12/2022 | ERIC WONG |
| Quality Review Completed | 11/17/2022 | PETER KIM |
| Building Plans Picked Up | 11/18/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 12/2/2022 | APPLICANT |
| Applicant returned to address corrections | 7/6/2023 | TU HUA |
| Applicant returned to address corrections | 7/13/2023 | TU HUA |
| Applicant returned to address corrections | 8/1/2023 | TU HUA |
| Plan Check Approved | 8/2/2023 | TU HUA |
| Issued | 10/4/2023 | APPLICANT |
| CofO in Progress | 6/8/2026 | DERRICK SPENCER |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/24/2023 | PEDRO AYALA |
| Community Plan Implem. Overlay | Cleared | 2/13/2023 | CAELAN RAFFERTY |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | ANTHONY MAINEZ |
| DAS Clearance | Cleared | 3/28/2023 | SHINE LIN |
| Low Impact Development | Cleared | 6/21/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | DARIN LAM |
Contact Information
| Contractor | Bernards Builders Inc; Lic. No.: 977134-B | 555 FIRST ST SAN FERNANDO, CA 91340 |
| Engineer | Toro,, Rodrigo Antonio; Lic. No.: S6043 | 22446 BASSETT STREET WEST HILLS, CA 91307 |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Partial Approval | DERRICK SPENCER |
| Final | 12/13/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/13/2023 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 12/13/2023 | Not Ready for Inspection | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 12/13/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/15/2023 | Conditional Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/19/2023 | Partial Approval | ALAN NOVAK |
| Final | 12/19/2023 | Not Ready for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 12/19/2023 | Approved | ALAN NOVAK |
| Reinforced Concrete Frame | 12/19/2023 | Approved | ALAN NOVAK |
| Structural Steel Frame | 12/19/2023 | Partial Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 1/22/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 2/20/2024 | No Access for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/20/2024 | No Access for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/18/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Partial Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | DERRICK SPENCER |
| Final | 9/29/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 4/9/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 6/2/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 6/4/2026 | OK to Issue CofO | DERRICK SPENCER |