5644 N STANSBURY AVE 91401
Certificate Information: 5644 N STANSBURY AVE 91401
- Application / Permit
- 22010-10000-05442
- Plan Check / Job No.
- B22LA22510
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan: New Detached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1(d)1, and (g)
- Permit Issued
- Issued on 4/12/2023
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | DAVID CASTILLO |
| Corrections Issued | 12/1/2022 | DAVID CASTILLO |
| Quality Review Completed | 1/3/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/2/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/14/2023 | DAVID CASTILLO |
| Plan Check Approved | 3/29/2023 | DAVID CASTILLO |
| Issued | 4/12/2023 | APPLICANT |
| CofO in Progress | 3/23/2026 | VINCENT HANLEY |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
| CofO Issued | 5/19/2026 | RUBEN SALAS |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/1/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 3/1/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/2/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 3/2/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Pinnacle Construction Group; Lic. No.: 1065333-B | 20695 S WESTERN AVE SUITE 136 TORRANCE, CA 90501 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/17/2023 | Conditional Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/21/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 5/10/2023 | Approved | RYAN SALAZAR |
| Gas Test | 5/17/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 5/17/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 5/17/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 5/22/2023 | Approved | RYAN SALAZAR |
| Sewer | 5/22/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/22/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/1/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 6/1/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/13/2023 | Conditional Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 6/13/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 7/3/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Approved | RYAN SALAZAR |
| Gas Test | 7/17/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | RYAN SALAZAR |
| Gas Test | 7/27/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | RYAN SALAZAR |
| Insulation | 8/2/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 8/2/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 8/2/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/10/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/25/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 1/18/2024 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 1/18/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 1/18/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 7/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 7/22/2024 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 7/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Service/Power Release | 7/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 7/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 3/20/2026 | Approved | VINCENT HANLEY |
| Final | 3/20/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/20/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/20/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/20/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/20/2026 | Approved | VINCENT HANLEY |