5644 N STANSBURY AVE 91401

Certificate Information: 5644 N STANSBURY AVE 91401

Application / Permit
22010-10000-05442
Plan Check / Job No.
B22LA22510
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPlan: New Detached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1(d)1, and (g)
Permit Issued
Issued on 4/12/2023
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 DAVID CASTILLO
Corrections Issued 12/1/2022 DAVID CASTILLO
Quality Review Completed 1/3/2023 CHIHARU SUZUKI
Applicant returned to address corrections 3/2/2023 DAVID CASTILLO
Applicant returned to address corrections 3/14/2023 DAVID CASTILLO
Plan Check Approved 3/29/2023 DAVID CASTILLO
Issued 4/12/2023 APPLICANT
CofO in Progress 3/23/2026 VINCENT HANLEY
Permit Finaled 5/19/2026 RUBEN SALAS
CofO Issued 5/19/2026 RUBEN SALAS
Permit Finaled 5/19/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/1/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/1/2022 COLIN LOREDO
Sewer availability Cleared 12/1/2022 COLIN LOREDO
Low Impact Development Cleared 3/1/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 3/2/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 3/2/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Pinnacle Construction Group; Lic. No.: 1065333-B 20695 S WESTERN AVE SUITE 136      TORRANCE, CA 90501
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/17/2023 Conditional Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 4/21/2023 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/21/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 5/10/2023 Approved RYAN SALAZAR
Gas Test 5/17/2023 Not Ready for Inspection MATTHEW NELSON
Sewer 5/17/2023 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 5/17/2023 Not Ready for Inspection MATTHEW NELSON
Gas Test 5/22/2023 Approved RYAN SALAZAR
Sewer 5/22/2023 Approved RYAN SALAZAR
Underground Mechanical 5/22/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/1/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 6/1/2023 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 6/1/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/13/2023 Conditional Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 6/13/2023 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 7/3/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Approved RYAN SALAZAR
Gas Test 7/17/2023 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 7/17/2023 Partial Approval RYAN SALAZAR
Gas Test 7/27/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/2/2023 Approved RYAN SALAZAR
Insulation 8/2/2023 Approved RYAN SALAZAR
Shower Pan 8/2/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 8/2/2023 Approved RYAN SALAZAR
Drywall Nailing 8/10/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/25/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 1/18/2024 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 1/18/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Final 1/18/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 7/22/2024 Not Ready for Inspection RYAN SALAZAR
Final 7/22/2024 Corrections Issued RYAN SALAZAR
HVAC-Final 7/22/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Not Ready RYAN SALAZAR
Service/Power Release 7/22/2024 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 7/22/2024 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 3/20/2026 Approved VINCENT HANLEY
Final 3/20/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/20/2026 Approved VINCENT HANLEY
PLUMBING-Final 3/20/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/20/2026 Approved VINCENT HANLEY
Smoke Detectors 3/20/2026 Approved VINCENT HANLEY