1477 W 185TH ST 90248
Certificate Information: 1477 W 185TH ST 90248
- Application / Permit
- 22010-10000-05431
- Plan Check / Job No.
- B22LA22455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2-story acceesory building with ADU (690 sf) per ordinance on 2nd floor and recreation (283 sf)/garage on 1st floor.
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Metro
- Current Status
- Issued on 6/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 11/29/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/2/2022 | CHARLES CHANG |
| Building Plans Picked Up | 12/28/2022 | APPLICANT |
| Applicant returned to address corrections | 4/17/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 4/19/2024 | FARSHAD ALIMOHAMADI |
| Issued | 6/7/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2023 | ANA SORIANO |
| Sewer availability | Cleared | 9/28/2023 | KHAING AYE |
| Address approval | Cleared | 3/11/2024 | KHAING AYE |
| Low Impact Development | Cleared | 3/14/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | KHAING AYE |
Contact Information
| Architect | Mclernon,, Myrle Dennis; Lic. No.: C22007 | MDM ARCHITECTS 759 W. LANCASTER BLVD. LANCASTER, CA 93534 |
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2024 | Corrections Issued | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/20/2024 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Deputy Wood Construction | 10/4/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 10/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/16/2024 | Partial Approval | BEN MOLSTAD |
| Underground Mechanical | 10/16/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 10/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 11/1/2024 | Approved | BEN MOLSTAD |
| Deputy Wood Construction | 1/3/2025 | Conditional Approval | BEN MOLSTAD |
| Deputy Wood Construction | 1/30/2025 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | BEN MOLSTAD |
| Green Building Rough | 2/18/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 2/18/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/12/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 3/12/2025 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 3/12/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/17/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 3/17/2025 | Approved | BEN MOLSTAD |
| Insulation | 3/25/2025 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 4/25/2025 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/12/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 8/7/2025 | Approved | BEN MOLSTAD |
| Final | 4/1/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/1/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/26/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 5/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |