1432 E 25TH ST 90011

Certificate Information: 1432 E 25TH ST 90011

Application / Permit
22010-10000-05420
Plan Check / Job No.
B22LA22421
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4 story, with a roof deck, Type VA, 55 units (43 L.I & 11 M.I) affordable apartment building per 12.22.A.25 & AB1763 incentives.
Permit Issued
Issued on 8/26/2024
Issuing Office
Current Status
Issued on 8/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 KESETE HAREGOT
Corrections Issued 11/14/2022 KESETE HAREGOT
Quality Review Completed 11/14/2022 RODOLFO ARIAS
Plan Check Approved 8/19/2024 KESETE HAREGOT
Issued 8/26/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/23/2022 CHRISTOPHER ROCHA
Highway dedication Cleared 12/7/2022 CHRISTOPHER ROCHA
Permit Cleared 12/7/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 1/11/2023 KURT CORRAL
Trees in Parkway Cleared 4/5/2023 ADALBERTO VERA
Historic Resource Verification Cleared 6/5/2023 MAX LODER
Fire Marshal Fire Life Safety Cleared 8/17/2023 RONILO MULAWIN
Eng Process Fee Ord 176,300 Cleared 9/14/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 10/10/2023 JESSICA OPINION
Green Code Cleared 10/11/2023 KESETE HAREGOT
Building over 36-ft Cleared 10/25/2023 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/26/2023 CALOSHA APPROVED
Density Bonus Cleared 11/22/2023 LOUIE MILLER
Redevelopment Project Area Cleared 11/30/2023 YASMINE BASHIRI
DAS Clearance Cleared 12/1/2023 ELIZABETH TOMS
Public Works-Highway Ded. Cleared 12/1/2023 CHRISTOPHER ROCHA
Frnt yard landscape/Water mgmt Cleared 12/4/2023 JAZMIN ROQUE
Opn space landscape/Water mgmt Cleared 12/4/2023 JAZMIN ROQUE
ZA Case Cleared 12/4/2023 JAZMIN ROQUE
Low Impact Development Cleared 5/15/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/23/2024 JESSICA OPINION

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: NA35389       ,
Contractor Bancomer Construction & Development; Lic. No.: 783429-B       ,
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Hu,, Yang Ming; Lic. No.: C81754 13675 HILL GROVE ST      CORONA, CA 92880
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Engineer Singer,, Joanne Chapin; Lic. No.: C26900 40530 KINSALE PL      INDIO, CA 92203

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2024 Not Ready for Inspection JAMES POWERS
Grading Pre-Inspection 9/12/2024 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 12/26/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/27/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/21/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 3/14/2025 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 6/5/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 6/5/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 6/5/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 6/5/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/9/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 6/9/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/12/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/16/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 6/20/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/25/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/25/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 7/3/2025 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/3/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 7/3/2025 Partial Approval JAMES POWERS
Insulation 9/9/2025 Partial Approval RAFAEL CORTES
Insulation 9/16/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 9/16/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 9/23/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 10/15/2025 Partial Approval RAFAEL CORTES
Insulation 10/30/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 11/26/2025 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 12/17/2025 Partial Approval RAFAEL CORTES