1432 E 25TH ST 90011
Certificate Information: 1432 E 25TH ST 90011
- Application / Permit
- 22010-10000-05420
- Plan Check / Job No.
- B22LA22421
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 4 story, with a roof deck, Type VA, 55 units (43 L.I & 11 M.I) affordable apartment building per 12.22.A.25 & AB1763 incentives.
- Permit Issued
- Issued on 8/26/2024
- Issuing Office
- Current Status
- Issued on 8/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | KESETE HAREGOT |
| Corrections Issued | 11/14/2022 | KESETE HAREGOT |
| Quality Review Completed | 11/14/2022 | RODOLFO ARIAS |
| Plan Check Approved | 8/19/2024 | KESETE HAREGOT |
| Issued | 8/26/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2022 | CHRISTOPHER ROCHA |
| Highway dedication | Cleared | 12/7/2022 | CHRISTOPHER ROCHA |
| Permit | Cleared | 12/7/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 1/11/2023 | KURT CORRAL |
| Trees in Parkway | Cleared | 4/5/2023 | ADALBERTO VERA |
| Historic Resource Verification | Cleared | 6/5/2023 | MAX LODER |
| Fire Marshal Fire Life Safety | Cleared | 8/17/2023 | RONILO MULAWIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/10/2023 | JESSICA OPINION |
| Green Code | Cleared | 10/11/2023 | KESETE HAREGOT |
| Building over 36-ft | Cleared | 10/25/2023 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 10/26/2023 | CALOSHA APPROVED |
| Density Bonus | Cleared | 11/22/2023 | LOUIE MILLER |
| Redevelopment Project Area | Cleared | 11/30/2023 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 12/1/2023 | ELIZABETH TOMS |
| Public Works-Highway Ded. | Cleared | 12/1/2023 | CHRISTOPHER ROCHA |
| Frnt yard landscape/Water mgmt | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Opn space landscape/Water mgmt | Cleared | 12/4/2023 | JAZMIN ROQUE |
| ZA Case | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Low Impact Development | Cleared | 5/15/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/23/2024 | JESSICA OPINION |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: NA35389 | , |
| Contractor | Bancomer Construction & Development; Lic. No.: 783429-B | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Hu,, Yang Ming; Lic. No.: C81754 | 13675 HILL GROVE ST CORONA, CA 92880 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Singer,, Joanne Chapin; Lic. No.: C26900 | 40530 KINSALE PL INDIO, CA 92203 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2024 | Not Ready for Inspection | JAMES POWERS |
| Grading Pre-Inspection | 9/12/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Steel/Welding | 12/26/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 12/27/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | RAFAEL CORTES |
| Special/Order Compliance | 3/14/2025 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 6/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 6/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 6/9/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Wood Frame | 6/9/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 6/12/2025 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 6/16/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 6/20/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 6/25/2025 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 6/25/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 7/3/2025 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/3/2025 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 7/3/2025 | Partial Approval | JAMES POWERS |
| Insulation | 9/9/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 9/16/2025 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 9/16/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 9/23/2025 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 10/15/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 10/30/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 11/26/2025 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | RAFAEL CORTES |