6622 N BLEWETT AVE 91406
Certificate Information: 6622 N BLEWETT AVE 91406
- Application / Permit
- 22010-10000-05413
- Plan Check / Job No.
- B22VN15808
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | DANIEL YIP |
| Corrections Issued | 10/29/2022 | DANIEL YIP |
| Quality Review Completed | 11/8/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/8/2024 | DANIEL YIP |
| Applicant returned to address corrections | 3/27/2024 | DANIEL YIP |
| Applicant returned to address corrections | 9/6/2024 | DANIEL YIP |
| Plan Check Approved | 9/27/2024 | DANIEL YIP |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 8/12/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
| CofO Issued | 9/25/2025 | RUBEN SALAS |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 11/23/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 11/23/2022 | BRENNEN OBETO |
| Low Impact Development | Cleared | 1/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | ROMAN GUTIERREZ |
| Construction within easement | Cleared | 2/9/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Italuce Construction And Development; Lic. No.: 924129-B | , |
| Contractor | Italuce Corporation; Lic. No.: 924129-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/2/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 2/10/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 2/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/6/2025 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 3/6/2025 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 3/6/2025 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/6/2025 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 3/6/2025 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/17/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Shower Pan | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/1/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/1/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/4/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Insulation | 4/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 4/8/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 4/22/2025 | Approved | LOUIS ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 4/22/2025 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 6/9/2025 | Corrections Issued | MICHAEL CORTEZ |
| Underground Mechanical | 6/11/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 6/20/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 6/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 6/20/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/29/2025 | Approved | SALVADOR MARTINEZ |
| Final | 7/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/29/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 7/29/2025 | Partial Inspection | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/29/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 7/29/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 8/1/2025 | Approved | SALVADOR MARTINEZ |
| Final | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 8/1/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 8/1/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 8/1/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/5/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Final | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 8/8/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/11/2025 | Approved | SALVADOR MARTINEZ |
| Final | 8/11/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| HVAC-Final | 8/11/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 8/11/2025 | Approved | SALVADOR MARTINEZ |