6622 N BLEWETT AVE 91406

Certificate Information: 6622 N BLEWETT AVE 91406

Application / Permit
22010-10000-05413
Plan Check / Job No.
B22VN15808
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 DANIEL YIP
Corrections Issued 10/29/2022 DANIEL YIP
Quality Review Completed 11/8/2022 GARO TELMI
Applicant returned to address corrections 3/8/2024 DANIEL YIP
Applicant returned to address corrections 3/27/2024 DANIEL YIP
Applicant returned to address corrections 9/6/2024 DANIEL YIP
Plan Check Approved 9/27/2024 DANIEL YIP
Issued 10/9/2024 APPLICANT
CofO in Progress 8/12/2025 SALVADOR MARTINEZ
Permit Finaled 9/25/2025 RUBEN SALAS
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/22/2022 ROMAN GUTIERREZ
Sewer availability Cleared 11/23/2022 ROMAN GUTIERREZ
ZI Cleared 11/23/2022 BRENNEN OBETO
Low Impact Development Cleared 1/17/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/26/2023 ROMAN GUTIERREZ
Construction within easement Cleared 2/9/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/22/2024 BRYAN GODINEZ

Contact Information

Contractor Italuce Construction And Development; Lic. No.: 924129-B       ,
Contractor Italuce Corporation; Lic. No.: 924129-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 11/26/2024 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 12/2/2024 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 2/10/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/12/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 2/28/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/6/2025 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/6/2025 Corrections Issued RAUL OLAGI
HVAC-Rough 3/6/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/6/2025 Approved RAUL OLAGI
Verify Sprinkler Sign Off 3/6/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/17/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 3/17/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/17/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/17/2025 Partial Approval GAREN HAYRAPETYAN
Shower Pan 3/17/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/1/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/1/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/4/2025 Partial Inspection SALVADOR MARTINEZ
Insulation 4/4/2025 Corrections Issued SALVADOR MARTINEZ
Insulation 4/8/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/18/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 4/22/2025 Approved LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 4/22/2025 Approved LOUIS ESCOTO
Underground Mechanical 6/9/2025 Corrections Issued MICHAEL CORTEZ
Underground Mechanical 6/11/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/20/2025 Approved JAVIER RAMOS JR
Final 6/20/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/20/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 6/20/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 6/20/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 6/20/2025 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 6/20/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/29/2025 Approved SALVADOR MARTINEZ
Final 7/29/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 7/29/2025 Approved SALVADOR MARTINEZ
HVAC-Final 7/29/2025 Partial Inspection SALVADOR MARTINEZ
PLUMBING-Final 7/29/2025 Approved SALVADOR MARTINEZ
Service/Power Release 7/29/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Final 8/1/2025 Approved SALVADOR MARTINEZ
Final 8/1/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 8/1/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 8/1/2025 Approved SALVADOR MARTINEZ
Service/Power Release 8/1/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 8/5/2025 Approved GAREN HAYRAPETYAN
Final 8/5/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 8/5/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 8/5/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/5/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 8/5/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 8/8/2025 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 8/11/2025 Approved SALVADOR MARTINEZ
Final 8/11/2025 OK to Issue CofO SALVADOR MARTINEZ
HVAC-Final 8/11/2025 Approved SALVADOR MARTINEZ
Service/Power Release 8/11/2025 Approved SALVADOR MARTINEZ