3405 N FRYMAN ROAD 91604

Certificate Information: 3405 N FRYMAN ROAD 91604

Application / Permit
22010-10000-05411
Plan Check / Job No.
B22LA22383
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 1) (N) 2-STORY SFD W/ATT 6-CAR GAR
Permit Issued
Issued on 8/16/2023
Issuing Office
Current Status
CofO Issued on 12/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 ARSALAN SHABESTARI
Corrections Issued 11/11/2022 ARSALAN SHABESTARI
Quality Review Completed 11/17/2022 GARO TELMI
Applicant returned to address corrections 5/9/2023 ARSALAN SHABESTARI
Plan Check Approved 8/10/2023 ARSALAN SHABESTARI
Issued 8/16/2023 APPLICANT
CofO in Progress 12/2/2025 CHRISTOPHE COCHRAN
Permit Finaled 12/10/2025 RUBEN SALAS
CofO Issued 12/10/2025 RUBEN SALAS
Permit Finaled 12/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/4/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 1/4/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 1/4/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 1/4/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 1/4/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 1/4/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/4/2023 CARLOS AGUILERA
Sewer availability Cleared 1/4/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/10/2023 GILBERT URREA
Low Impact Development Cleared 2/17/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/27/2023 CARLOS AGUILERA
Landscape for retaining wall Cleared 4/12/2023 STEVEN WECHSLER
GPI Written Notices Cleared 4/20/2023 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 4/20/2023 ARSALAN SHABESTARI
Excavation more than 5-ft deep Cleared 5/10/2023 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/5/2024 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 1/19/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 1/25/2024 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 1/25/2024 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/30/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 1/31/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/2/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/28/2024 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 3/28/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 No Access for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 4/3/2024 Approved JOHN COLEMAN
Deputy Wood Construction 4/29/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 5/28/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/9/2024 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 9/4/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 9/5/2024 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 9/6/2024 Approved CHRISTOPHE COCHRAN
Pre-Inspection 9/13/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/23/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Pre-Inspection 9/24/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/27/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 9/27/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/30/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 9/30/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 9/30/2024 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 10/8/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 10/8/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/8/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/10/2024 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/14/2024 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 11/21/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 11/22/2024 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/27/2024 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 12/2/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/13/2024 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 12/19/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/23/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/11/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 6/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/22/2025 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 7/22/2025 Approved CHRISTOPHE COCHRAN
HVAC-Final 7/23/2025 Approved CHRISTOPHE COCHRAN
Final 9/12/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 9/12/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 9/12/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 9/12/2025 Approved CHRISTOPHE COCHRAN
Final 9/17/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 9/17/2025 Approved CHRISTOPHE COCHRAN