1321 N JUNE ST 1-3 90028
Certificate Information: 1321 N JUNE ST 1-3 90028
- Application / Permit
- 22010-10000-05406
- Plan Check / Job No.
- B22LA22370
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan - (n) 3-story duplex on 2nd and 3rd flr, (n) attached ADU with open garage at 1st flr per LAMC 12.22 A.33(c)(e)
- Permit Issued
- Issued on 11/15/2023
- Issuing Office
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | KELVIN CHUONG |
| Corrections Issued | 11/14/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/17/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/3/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/18/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/11/2023 | KELVIN CHUONG |
| Plan Check Approved | 5/24/2023 | KELVIN CHUONG |
| Issued | 11/15/2023 | APPLICANT |
| CofO in Progress | 12/13/2024 | BRIAN SULLIVAN |
| Permit Finaled | 12/31/2024 | DEROLD HAUFF |
| CofO Issued | 12/31/2024 | DEROLD HAUFF |
| Permit Finaled | 12/31/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/23/2022 | LAVEON RIDER |
| Address approval | Cleared | 11/26/2022 | STEVE MELGAR |
| Permit | Cleared | 11/26/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/29/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/27/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/23/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/28/2023 | STEVE MELGAR |
| Historic Resource Verification | Cleared | 3/1/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 3/6/2023 | DAVID URITA |
| ZI | Cleared | 3/6/2023 | DAVID URITA |
| DAS Clearance | Cleared | 3/16/2023 | Samuel Gonzalez |
| SB8 RUD | Cleared | 3/16/2023 | RICHARD TRUONG |
| Green Code | Cleared | 3/22/2023 | Samuel Gonzalez |
| Trees in Parkway | Cleared | 3/30/2023 | ADALBERTO VERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: NA33220 | , |
| Contractor | Alpha Build & Design Inc; Lic. No.: 398659-B | , |
| Contractor | Oravecz Contractors & Developers; Lic. No.: 398659-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/11/2024 | Partial Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 1/31/2024 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Other (see comments) | 4/3/2024 | Conditional Approval | ROY SPAULDING |
| Deputy Steel/Welding | 4/3/2024 | Conditional Approval | ROY SPAULDING |
| Deputy Steel/Welding | 4/5/2024 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | BRIAN SULLIVAN |
| Green Building Rough | 5/17/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 5/17/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 5/17/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 6/20/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 7/1/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 7/2/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 7/5/2024 | Conditional Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/13/2024 | Partial Approval | WILLIAM WREN |
| Insulation | 7/30/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Final | 12/12/2024 | OK to Issue CofO | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Green Building Final | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 12/12/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Wood Frame | 12/12/2024 | Approved | BRIAN SULLIVAN |