5351-5355 W PACKARD ST 90019

Certificate Information: 5351-5355 W PACKARD ST 90019

Application / Permit
22010-10000-05405
Plan Check / Job No.
B22LA22368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION TO AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 2/6/2023
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 DANIEL ABRAMYAN
Corrections Issued 11/14/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 12/16/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 1/10/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 1/20/2023 MOHAMMAD ESMAILI
Plan Check Approved 1/28/2023 MOHAMMAD ESMAILI
Issued 2/6/2023 APPLICANT
CofO in Progress 11/9/2023 JOSE AVILA
Permit Finaled 11/18/2023 DEROLD HAUFF
Permit Finaled 11/18/2023 DEROLD HAUFF
CofO Issued 11/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/18/2022 STEVE MELGAR
Address approval Cleared 1/3/2023 STEVE MELGAR
Sewer availability Cleared 1/5/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/6/2023 STEVE MELGAR

Contact Information

Contractor Mr Build Home Improvement Company; Lic. No.: 439166-B       ,
Contractor Mr Build Solar Electric; Lic. No.: 439166-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2023 Partial Inspection JOSE AVILA
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 4/14/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 4/26/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 5/4/2023 Approved STUART CHAPMAN
METHANE-Barrier 5/4/2023 Approved STUART CHAPMAN
METHANE-Subgrade 5/4/2023 Approved STUART CHAPMAN
PLUMBING-Rough 6/5/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/12/2023 Corrections Issued JOSE AVILA
HVAC-Rough 6/12/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/12/2023 Partial Approval JOSE AVILA
Wood Frame 6/12/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 6/16/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/16/2023 Approved JOSE AVILA
Green Building Rough 6/16/2023 Corrections Issued JOSE AVILA
HVAC-Rough 6/16/2023 Approved JOSE AVILA
METHANE-Rough 6/16/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 6/23/2023 Conditional Approval LILIANA PORTILLO
Insulation 6/23/2023 Approved LILIANA PORTILLO
Green Building Rough 6/26/2023 Approved JOSE AVILA
Interior/Exterior Lathing 6/26/2023 Not Ready for Inspection JOSE AVILA
Drywall Nailing 6/30/2023 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 6/30/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 7/11/2023 Approved KRISTEN CAUSEY
Shower Pan 7/11/2023 Approved KRISTEN CAUSEY
Final 10/2/2023 No Access for Inspection JOSE AVILA
BUILDING-Rough-Frame 10/4/2023 Approved JOSE AVILA
Final 10/4/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready JOSE AVILA
Smoke Detectors 10/4/2023 Approved JOSE AVILA
Final 10/23/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Final 10/26/2023 Approved JOSE AVILA
Gas Test 10/26/2023 Approved JOSE AVILA
Service/Power Release 10/26/2023 Approved JOSE AVILA
Final 11/9/2023 OK to Issue CofO JOSE AVILA
Green Building Final 11/9/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved JOSE AVILA
Service/Power Release 11/11/2023 Approved JOSE AVILA