11541 W KLING ST 91602
Certificate Information: 11541 W KLING ST 91602
- Application / Permit
- 22010-10000-05391
- Plan Check / Job No.
- B22VN15345
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- EPLAN. 2. Recreation Room (13' x 19'6")
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | NGHI SU |
| Corrections Issued | 11/3/2022 | NGHI SU |
| Quality Review Completed | 11/3/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/30/2023 | NGHI SU |
| Plan Check Approved | 2/7/2023 | NGHI SU |
| Plan Check Approved | 2/22/2023 | NGHI SU |
| Plan Check Approved | 3/3/2023 | NGHI SU |
| Plan Check Approved | 3/7/2023 | NGHI SU |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 7/23/2024 | CHRISTOPHER ROJAS |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/5/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/17/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 1/4/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/10/2023 | MAXFIELD VERMY |
| ZI | Cleared | 1/12/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 1/12/2023 | JOANNA MARROQUIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/31/2023 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/10/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 8/1/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/3/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 8/17/2023 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/25/2023 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 8/28/2023 | Approved | JACK KARGODORIAN |
| Insulation | 9/1/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 9/1/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 9/8/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/12/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 5/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 5/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 5/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 6/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 6/17/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 6/17/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 6/17/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/22/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |