3566 N OAKFIELD DR 91423

Certificate Information: 3566 N OAKFIELD DR 91423

Application / Permit
22010-10000-05382
Plan Check / Job No.
B22LA22265
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONSTRUCTION OF A NEW, 5,101 SF (43'0" x 127'9"), TWO-STORY, SINGLE-FAMILY RESIDENCE WITH 1627 SF SIX-CAR GARAGE AT THE BASEMENT LEVEL. NFPA 13R FIRE SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
Issued on 4/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 NGHI SU
Corrections Issued 12/1/2022 NGHI SU
Quality Review Completed 12/1/2022 GARO TELMI
Applicant returned to address corrections 1/17/2023 NGHI SU
Applicant returned to address corrections 2/15/2023 NGHI SU
Applicant returned to address corrections 4/24/2023 NGHI SU
Applicant returned to address corrections 5/18/2023 NGHI SU
Plan Check Approved 4/16/2024 NGHI SU
Issued 4/17/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/17/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/21/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/18/2023 RUEL COLE
Disturb/Remove Protected Trees Cleared 6/5/2023 ADALBERTO VERA
Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
Landscape for retaining wall Cleared 6/15/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 6/15/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 6/15/2023 NELSON RODRIGUEZ
Specific Plan Cleared 6/15/2023 NELSON RODRIGUEZ
Excavation more than 5-ft deep Cleared 7/6/2023 CALOSHA APPROVED
Low Impact Development (LID) Cleared 9/22/2023 ROGELIO CORTES
BHO/Hillside ordinance Cleared 11/29/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/29/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/29/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/29/2023 CARLOS AGUILERA
Permit Cleared 11/29/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/29/2023 CARLOS AGUILERA
Sewer availability Cleared 11/29/2023 CARLOS AGUILERA
Street Frontage Cleared 11/29/2023 CARLOS AGUILERA
Building over 36-ft Cleared 12/28/2023 CALOSHA APPROVED
GPI Written Notices Cleared 12/28/2023 NGHI SU
Grading Pre-Inspection Cleared 12/28/2023 NGHI SU

Contact Information

Contractor Owner-Builder       ,
Engineer Ahmed,, Zafar; Lic. No.: GE2720 113 TOMATO SPRINGS      IRVINE, CA 92618
Engineer Andrada,, Aprile; Lic. No.: C81097 27240 TURNBERRY LANE      VALENCIA, CA 91355
Engineer Chen,, Shaofu; Lic. No.: C76834 5589 CARMELLO COURT      RANCHO CUCAMONGA, CA 91739
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Geologist Aflakian,, Farzad; Lic. No.: EG2051 921 PENDIO      IRVINE, CA 92620
Geologist Chen,, Shaofu; Lic. No.: EG2688 5589 CARMELLO COURT      RANCHO CUCAMONGA, CA 91739
Landscape Architect Savage,, Michael Sanford; Lic. No.: LA4397 1125 SHEPPARD DRIVE      FULLERTON, CA 92831

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/20/2024 Corrections Issued MISAEL ESPARZA
Piling/Pier/Caisson 6/20/2024 Not Ready for Inspection MISAEL ESPARZA
Deputy Reinf. Concrete 6/25/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/28/2024 Approved JACK KARGODORIAN
Piling/Pier/Caisson 6/28/2024 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 7/2/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/14/2024 Partial Approval MISAEL ESPARZA
Deputy Shotcrete 8/20/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/27/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/13/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 10/18/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/1/2024 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 11/7/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/13/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/22/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/4/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/4/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/4/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/24/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 6/24/2025 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 6/24/2025 Approved JUAN VALENZUELA
Pre-Inspection 6/24/2025 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 7/17/2025 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 7/18/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/5/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/5/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 8/5/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/29/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 9/29/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 9/29/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/9/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/9/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/9/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 10/22/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/22/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/22/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/30/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/30/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/30/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 10/30/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 10/30/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 10/30/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 11/3/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 11/3/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/14/2025 Partial Approval JOSE AVILA
HVAC-Rough 11/21/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/21/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 11/24/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/26/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/26/2025 Approved MISAEL ESPARZA
Green Building Rough 11/26/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 11/26/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/8/2025 Corrections Issued MISAEL ESPARZA
Insulation 12/8/2025 Partial Approval MISAEL ESPARZA
Insulation 12/12/2025 Corrections Issued MISAEL ESPARZA
Shower Pan 12/12/2025 Corrections Issued MISAEL ESPARZA
Insulation 12/16/2025 Corrections Issued MISAEL ESPARZA
Shower Pan 12/16/2025 Not Ready for Inspection MISAEL ESPARZA
Insulation 12/18/2025 Approved MISAEL ESPARZA
Shower Pan 12/18/2025 Corrections Issued MISAEL ESPARZA
Shower Pan 12/23/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/31/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 1/7/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 1/7/2026 Approved MISAEL ESPARZA
Drywall Nailing 1/13/2026 Approved MISAEL ESPARZA