4532 N KATHERINE AVE 91423
Certificate Information: 4532 N KATHERINE AVE 91423
- Application / Permit
- 22010-10000-05348
- Plan Check / Job No.
- B22LA22120
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-STORY House (SFD) W/ ATTACHED GARAGE
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | JOE VO |
| Corrections Issued | 11/5/2022 | JOE VO |
| Quality Review Completed | 11/7/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/15/2023 | JOE VO |
| Plan Check Approved | 2/21/2023 | JOE VO |
| Issued | 2/22/2023 | APPLICANT |
| CofO in Progress | 5/21/2025 | MISAEL ESPARZA |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/13/2022 | RUEL COLE |
| Address approval | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Permit | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/5/2023 | CARLOS AGUILERA |
| ZI | Cleared | 1/30/2023 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 2/3/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/3/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/6/2023 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/29/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 11/17/2023 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 12/13/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 2/21/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/8/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 3/12/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/14/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/14/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 3/14/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/14/2024 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 3/15/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/22/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 4/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 4/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | MISAEL ESPARZA |
| Insulation | 4/22/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/22/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 4/22/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 5/1/2024 | Approved | MISAEL ESPARZA |
| Sewer | 5/1/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/1/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 5/10/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/10/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/21/2024 | Approved | LEONARD ROSS II |
| PLUMBING-Final | 10/25/2024 | Approved | VINCENT HANLEY |
| Gas Test | 10/30/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 11/13/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 11/13/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/18/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 12/18/2024 | Approved | MISAEL ESPARZA |
| Final | 1/17/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/17/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 1/17/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 1/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 1/17/2025 | Approved | MISAEL ESPARZA |
| Final | 5/19/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 5/19/2025 | Approved | MISAEL ESPARZA |