10705 S AVALON BLVD 1-69 90003

Certificate Information: 10705 S AVALON BLVD 1-69 90003

Application / Permit
22010-10000-05321
Plan Check / Job No.
B22LA21971
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY WITH ROOF DECK 69 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT, Density Bonus per Sec. 12.22A25 ED1 project.
Permit Issued
Issued on 9/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 ARMEN JIVALAGIAN
Corrections Issued 11/8/2022 ARMEN JIVALAGIAN
Quality Review Completed 11/17/2022 PETER KIM
Applicant returned to address corrections 12/16/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/31/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/3/2023 ARMEN JIVALAGIAN
Plan Check Approved 6/28/2023 ARMEN JIVALAGIAN
Issued 9/11/2023 APPLICANT
TCO Issued (Expire Date: 02-23-2026) 8/27/2025 ERNESTO CORRAL
CofO in Progress 9/24/2025 JAMES POWERS
Permit Finaled 9/24/2025 ERNESTO CORRAL
CofO Issued 9/24/2025 ERNESTO CORRAL
Permit Finaled 9/24/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/3/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/5/2023 WALLIE JONG
Highway dedication Cleared 1/5/2023 WALLIE JONG
Watercourse Cleared 2/8/2023 TERRY PHAN
Hydrant and Access approval Cleared 2/10/2023 LAVEON RIDER
Permit Cleared 2/21/2023 TREVOR QUAN
Trees in Parkway Cleared 3/16/2023 ADALBERTO VERA
Low Impact Development Cleared 3/21/2023 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/21/2023 WALLIE JONG
Sewer availability Cleared 3/24/2023 WALLIE JONG
Building over 36-ft Cleared 3/29/2023 CALOSHA APPROVED
"Q" conditions Cleared 3/30/2023 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 3/30/2023 JASON CHAN
Opn space landscape/Water mgmt Cleared 3/30/2023 JASON CHAN
Site Plan review Cleared 3/30/2023 JASON CHAN
Miscellaneous Cleared 3/31/2023 JASON CHAN
Construction near power lines Cleared 4/7/2023 RIDWAN HARDY
Construction within easement Cleared 4/7/2023 RIDWAN HARDY
Green Code Cleared 4/13/2023 ARMEN JIVALAGIAN
Fire Marshal Fire Life Safety Cleared 5/5/2023 MENOA AGHAJANI
DCP conditions approval Cleared 5/16/2023 KENNETH LE
Density Bonus Cleared 5/16/2023 KENNETH LE
SB8 RUD Cleared 5/16/2023 KENNETH LE
DAS Clearance Cleared 6/1/2023 ARMEN JIVALAGIAN

Contact Information

Contractor Steiner Douglas Construction Inc; Lic. No.: 916002-B       ,
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2023 Approved JAMES POWERS
Footing/Foundation/Slab 10/19/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/6/2023 Partial Inspection LARRY ARNICK
Pre-Inspection 11/6/2023 Partial Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/8/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 11/9/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/9/2023 Approved LARRY ARNICK
Footing/Foundation/Slab 11/9/2023 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 11/29/2023 Not Ready for Inspection JAMES POWERS
Pre-Inspection 11/29/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/5/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2023 Partial Approval JAMES POWERS
Pre-Inspection 12/13/2023 Partial Approval JAMES POWERS
Structural Steel Frame 12/13/2023 Approved JAMES POWERS
Deputy Drilled-In Anchors 12/15/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 12/21/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Partial Approval JAMES POWERS
Wood Frame 12/27/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Partial Approval JAMES POWERS
Wood Frame 1/4/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval JAMES POWERS
Wood Frame 1/23/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval JAMES POWERS
Wood Frame 1/24/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval JAMES POWERS
Wood Frame 2/7/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval MARTIN TAVITIAN
Wood Frame 2/23/2024 Partial Inspection MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Inspection JEFFREY FULTON
Wood Frame 3/4/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 3/13/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval JAMES POWERS
Wood Frame 3/27/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval JAMES POWERS
Wood Frame 4/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 4/29/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 5/1/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval JAMES POWERS
Insulation 5/9/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 5/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 5/13/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 5/14/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval LARRY ARNICK
Drywall Nailing 5/23/2024 Not Ready for Inspection LARRY ARNICK
Insulation 5/23/2024 Not Ready for Inspection LARRY ARNICK
Wall Anchors 5/23/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/23/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/24/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Not Ready for Inspection LARRY ARNICK
Insulation 5/24/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/24/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval JAMES POWERS
Insulation 6/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Not Ready for Inspection JAMES POWERS
Insulation 6/4/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 6/4/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 6/10/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval JAMES POWERS
Wood Frame 6/11/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 6/12/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/20/2024 Partial Approval JAMES POWERS
Insulation 6/21/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 6/21/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Not Ready for Inspection JAMES POWERS
Insulation 6/27/2024 Partial Approval JAMES POWERS
Wood Frame 6/27/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/31/2024 No Access for Inspection DANIEL VARNUM
Insulation 7/31/2024 No Access for Inspection DANIEL VARNUM
Drywall Nailing 8/2/2024 Partial Approval JAMES POWERS
Insulation 8/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/12/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/27/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 8/27/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/4/2024 Partial Approval JAMES POWERS
Insulation 9/4/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/17/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/17/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 9/17/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/26/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/26/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/1/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/2/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/8/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/8/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/21/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/21/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/23/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/28/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/28/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/4/2024 Not Ready for Inspection JAMES POWERS
Insulation 11/5/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/5/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/13/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/13/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/15/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/18/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 11/18/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 11/20/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/2/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/3/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/3/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/3/2025 Partial Approval JAMES POWERS
Insulation 1/3/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/3/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/14/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/16/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/31/2025 Not Ready for Inspection JAMES POWERS
Insulation 1/31/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/18/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/26/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/28/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/21/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved JAMES POWERS
Drywall Nailing 3/26/2025 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/26/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/2/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 4/2/2025 Partial Approval JAMES POWERS
Wood Frame 4/3/2025 Approved JAMES POWERS
Drywall Nailing 4/10/2025 Partial Approval JAMES POWERS
Wood Frame 4/16/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/18/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Approved JAMES POWERS
Light Gage Steel Frame 4/18/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/23/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 5/5/2025 Partial Approval JAMES POWERS
Pre-Inspection 5/9/2025 Partial Approval JAMES POWERS
Drywall Nailing 5/21/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/28/2025 Partial Approval JAMES POWERS
Final 6/16/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/20/2025 Partial Approval JAMES POWERS
Pre-Inspection 7/2/2025 Not Ready for Inspection JAMES POWERS
Final 7/31/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/31/2025 Approved JAMES POWERS
Green Building Final 7/31/2025 Approved JAMES POWERS
Green Building Rough 7/31/2025 Approved JAMES POWERS
Reinforced Masonry Frame 7/31/2025 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Not Ready JAMES POWERS
Smoke Detectors 7/31/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/31/2025 Not Ready for Inspection JAMES POWERS
Final 8/8/2025 OK for TCO JAMES POWERS
Reinforced Masonry Frame 8/8/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved JAMES POWERS
Verify Sprinkler Sign Off 8/8/2025 Approved JAMES POWERS
Final 8/14/2025 OK for TCO JAMES POWERS
Final 8/20/2025 OK for TCO JAMES POWERS
Final 9/8/2025 OK for TCO JAMES POWERS
Final 9/24/2025 OK to Issue CofO JAMES POWERS