1736 S CARMONA AVE 90019
Certificate Information: 1736 S CARMONA AVE 90019
- Application / Permit
- 22010-10000-05309
- Plan Check / Job No.
- B22LA21922
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING W/ ATTACHED 1 CAR GARAGE @ FRONT OF PROPERTY R3-OCCUPANCY: 2070 SQFT U-OCCUPANCY: 162 SQFT
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | JAD BASMA |
| Corrections Issued | 11/6/2022 | JAD BASMA |
| Quality Review Completed | 11/14/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 11/16/2022 | APPLICANT |
| Applicant returned to address corrections | 3/23/2023 | JAD BASMA |
| Applicant returned to address corrections | 3/29/2023 | JAD BASMA |
| Plan Check Approved | 4/20/2023 | JAD BASMA |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 9/20/2024 | ARTHUR NEGRETE |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
| CofO Issued | 12/12/2024 | DEROLD HAUFF |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2022 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 12/2/2022 | DEBORA LEITE |
| Frnt yard landscape/Water mgmt | Cleared | 12/4/2022 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/6/2022 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 1/11/2023 | KURT CORRAL |
| SB8 RUD | Cleared | 3/2/2023 | SALLY LIANG |
Contact Information
| Contractor | Safe Quake Construction; Lic. No.: 571102-B | 2088 S ATLANTIC BL #291 MONTEREY PARK, CA 91754 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 8/15/2023 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Not Ready for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 8/24/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/25/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 8/29/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 1/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 1/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/31/2024 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/31/2024 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 1/31/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/31/2024 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 1/31/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/8/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 2/8/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 2/8/2024 | Approved | BRENDAN MORELLI |
| Wood Frame | 2/8/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/9/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 2/9/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/9/2024 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/9/2024 | Approved | STUART CHAPMAN |
| Insulation | 2/14/2024 | No Access for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/14/2024 | No Access for Inspection | STUART CHAPMAN |
| Insulation | 2/15/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/15/2024 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 2/23/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 2/23/2024 | Approved | STUART CHAPMAN |
| Sewer | 4/29/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/9/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 7/9/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/23/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 7/23/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 7/23/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | ARTHUR NEGRETE |
| Gas Test | 8/19/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 8/19/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/19/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/27/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Gas Test | 8/27/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/27/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 8/27/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 9/11/2024 | Approved | ARTHUR NEGRETE |
| Final | 9/11/2024 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 9/11/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 9/11/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 9/11/2024 | Approved | ARTHUR NEGRETE |
| Final | 9/19/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Service/Power Release | 9/19/2024 | Approved | ARTHUR NEGRETE |