5527 W 83RD ST 90045
Certificate Information: 5527 W 83RD ST 90045
- Application / Permit
- 22010-10000-05272
- Plan Check / Job No.
- B22LA21760
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 20'x20' detached one story ADU per State Law GCS 65852.2(e)(1)(B)& LAMC 12.22 A.33(c), (d) and (g)
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | AUNG SOE |
| Corrections Issued | 11/8/2022 | AUNG SOE |
| Building Plans Picked Up | 11/15/2022 | APPLICANT |
| Plan Check Approved | 8/14/2023 | ZAW HAN |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 9/10/2024 | BOBBY KEY |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
| CofO Issued | 9/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/24/2023 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/30/2023 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 2/6/2023 | RYAN LY |
| Miscellaneous | Cleared | 2/10/2023 | NOAH MCCOY |
| Miscellaneous | Cleared | 2/10/2023 | NOAH MCCOY |
| Grading Pre-Inspection | Cleared | 2/14/2023 | KIRK LINKLATER |
| Construction near power lines | Cleared | 2/21/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/21/2023 | RIDWAN HARDY |
| Address approval | Cleared | 3/9/2023 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 4/2/2023 | RYAN LY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/13/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/15/2023 | Partial Approval | BOBBY KEY |
| METHANE-Subgrade | 9/21/2023 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 9/29/2023 | Corrections Issued | BOBBY KEY |
| METHANE-Barrier | 9/29/2023 | Corrections Issued | BOBBY KEY |
| METHANE-Subgrade | 9/29/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| METHANE-Barrier | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 12/1/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 12/5/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 12/5/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 12/5/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 12/11/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 12/11/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 12/11/2023 | Approved | BOBBY KEY |
| Insulation | 12/11/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 12/11/2023 | Partial Approval | BOBBY KEY |
| METHANE-Rough | 12/11/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 12/14/2023 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/19/2023 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 12/19/2023 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 12/19/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/19/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 12/29/2023 | Approved | BOBBY KEY |
| Insulation | 12/29/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/29/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 12/29/2023 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 1/3/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/22/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 1/31/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Shower Pan | 2/13/2024 | Approved | BOBBY KEY |
| Gas Test | 2/21/2024 | Not Ready for Inspection | BOBBY KEY |
| Sewer | 2/21/2024 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 2/21/2024 | Corrections Issued | BOBBY KEY |
| Gas Test | 2/26/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 2/26/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 2/26/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 2/28/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 5/2/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 5/16/2024 | Corrections Issued | BOBBY KEY |
| Final | 5/16/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/16/2024 | Approved | BOBBY KEY |
| HVAC-Final | 5/16/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/16/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 5/16/2024 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 5/16/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/12/2024 | Approved | BOBBY KEY |
| Final | 9/10/2024 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 9/10/2024 | Approved | BOBBY KEY |