5527 W 83RD ST 90045

Certificate Information: 5527 W 83RD ST 90045

Application / Permit
22010-10000-05272
Plan Check / Job No.
B22LA21760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 20'x20' detached one story ADU per State Law GCS 65852.2(e)(1)(B)& LAMC 12.22 A.33(c), (d) and (g)
Permit Issued
Issued on 8/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 AUNG SOE
Corrections Issued 11/8/2022 AUNG SOE
Building Plans Picked Up 11/15/2022 APPLICANT
Plan Check Approved 8/14/2023 ZAW HAN
Issued 8/17/2023 APPLICANT
CofO in Progress 9/10/2024 BOBBY KEY
Permit Finaled 9/16/2024 RICHARD STEINBACH
CofO Issued 9/16/2024 RICHARD STEINBACH
Permit Finaled 9/16/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 1/24/2023 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 1/30/2023 HISASHI KOBAYAKAWA
Sewer availability Cleared 1/30/2023 HISASHI KOBAYAKAWA
ZA Case Cleared 2/6/2023 RYAN LY
Miscellaneous Cleared 2/10/2023 NOAH MCCOY
Miscellaneous Cleared 2/10/2023 NOAH MCCOY
Grading Pre-Inspection Cleared 2/14/2023 KIRK LINKLATER
Construction near power lines Cleared 2/21/2023 RIDWAN HARDY
Construction within easement Cleared 2/21/2023 RIDWAN HARDY
Address approval Cleared 3/9/2023 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 3/15/2023 HISASHI KOBAYAKAWA
Miscellaneous Cleared 4/2/2023 RYAN LY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/13/2023 No Access for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 9/15/2023 Partial Approval BOBBY KEY
METHANE-Subgrade 9/21/2023 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 9/29/2023 Approved BOBBY KEY
Footing/Foundation/Slab 9/29/2023 Corrections Issued BOBBY KEY
METHANE-Barrier 9/29/2023 Corrections Issued BOBBY KEY
METHANE-Subgrade 9/29/2023 Approved BOBBY KEY
Footing/Foundation/Slab 10/6/2023 Approved JESUS RODRIGUEZ
METHANE-Barrier 10/6/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Approved TEMISTOCLES CAAL
Special/Order Compliance 12/1/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 12/5/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Approved BOBBY KEY
HVAC-Rough 12/5/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 12/5/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 12/11/2023 Not Ready for Inspection BOBBY KEY
Green Building Rough 12/11/2023 Approved BOBBY KEY
HVAC-Rough 12/11/2023 Approved BOBBY KEY
Insulation 12/11/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 12/11/2023 Partial Approval BOBBY KEY
METHANE-Rough 12/11/2023 Approved BOBBY KEY
Drywall Nailing 12/14/2023 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/19/2023 Not Ready for Inspection BOBBY KEY
Drywall Nailing 12/19/2023 Not Ready for Inspection BOBBY KEY
Insulation 12/19/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 12/19/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 12/29/2023 Approved BOBBY KEY
Insulation 12/29/2023 Approved BOBBY KEY
PLUMBING-Rough 12/29/2023 Approved BOBBY KEY
Special/Order Compliance 12/29/2023 Corrections Issued BOBBY KEY
Drywall Nailing 1/3/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/22/2024 Approved JESUS RODRIGUEZ
Shower Pan 1/22/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 1/31/2024 Not Ready for Inspection TEMISTOCLES CAAL
Shower Pan 2/13/2024 Approved BOBBY KEY
Gas Test 2/21/2024 Not Ready for Inspection BOBBY KEY
Sewer 2/21/2024 Not Ready for Inspection BOBBY KEY
Special/Order Compliance 2/21/2024 Corrections Issued BOBBY KEY
Gas Test 2/26/2024 Approved TEMISTOCLES CAAL
Sewer 2/26/2024 Not Ready for Inspection TEMISTOCLES CAAL
Underground Mechanical 2/26/2024 Not Ready for Inspection TEMISTOCLES CAAL
Underground Mechanical 2/28/2024 Partial Approval BOBBY KEY
ELECTRICAL-Final 5/2/2024 Partial Approval BOBBY KEY
ELECTRICAL-Final 5/16/2024 Corrections Issued BOBBY KEY
Final 5/16/2024 Corrections Issued BOBBY KEY
Green Building Final 5/16/2024 Approved BOBBY KEY
HVAC-Final 5/16/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 5/16/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved BOBBY KEY
Service/Power Release 5/16/2024 Not Ready for Inspection BOBBY KEY
Smoke Detectors 5/16/2024 Approved BOBBY KEY
ELECTRICAL-Final 8/12/2024 Approved BOBBY KEY
Final 9/10/2024 OK to Issue CofO BOBBY KEY
Service/Power Release 9/10/2024 Approved BOBBY KEY