584 W 38TH ST 90731
Certificate Information: 584 W 38TH ST 90731
- Application / Permit
- 22010-10000-05267
- Plan Check / Job No.
- B22LA21724
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: new detached 740 sq ft (irregular shape 16' x 23'4") two story ADU
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- CofO Issued on 11/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | NGHI SU |
| Corrections Issued | 11/18/2022 | NGHI SU |
| Quality Review Completed | 11/23/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/9/2023 | NGHI SU |
| Plan Check Approved | 7/17/2023 | NGHI SU |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 11/26/2024 | JOSEPH MCGARRY |
| CofO Issued | 11/27/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/27/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2023 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/23/2023 | KHAING AYE |
| Sewer availability | Cleared | 3/23/2023 | KHAING AYE |
| Miscellaneous | Cleared | 6/26/2023 | DALIA MOKAYED |
| Coastal Zone | Cleared | 7/3/2023 | CLAUDE GOODING |
| Miscellaneous | Cleared | 7/3/2023 | CLAUDE GOODING |
| GPI Written Notices | Cleared | 7/17/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 7/17/2023 | NGHI SU |
| Zoning Information File | Cleared | 7/17/2023 | NGHI SU |
Contact Information
| Architect | James,, William Douglas; Lic. No.: C28863 | 415 W NINTH STREET SAN PEDRO, CA 90731 |
| Contractor | Agrusa General Contracting; Lic. No.: 972732-B | , |
| Engineer | Lombera,, Raymundo Alcaraz; Lic. No.: L7740 | 135 S JACKSON STREET #202 GLENDALE, CA 91205 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Partial Approval | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 10/23/2023 | Approved | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 10/30/2023 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/3/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Steel/Welding | 11/3/2023 | Conditional Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 11/3/2023 | Partial Approval | JAMES CHAVEZ |
| Sewer | 11/3/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 11/3/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 11/3/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 2/13/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/26/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 2/26/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 2/26/2024 | Approved | JAMES CHAVEZ |
| Insulation | 3/5/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/12/2024 | Approved | JAMES CHAVEZ |
| Shower Pan | 3/12/2024 | Corrections Issued | JAMES CHAVEZ |
| Interior/Exterior Lathing | 5/7/2024 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 5/7/2024 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | JOSEPH MCGARRY |
| Final | 11/21/2024 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 11/21/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 11/21/2024 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 11/21/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 11/21/2024 | Approved | JOSEPH MCGARRY |
| Final | 11/26/2024 | OK to Issue CofO | JOSEPH MCGARRY |