17057 W RANCHO ST 91316
Certificate Information: 17057 W RANCHO ST 91316
- Application / Permit
- 22010-10000-05262
- Plan Check / Job No.
- B22LA19403
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 2/. New Detached 1-Story ADU Type VB R-3 Occupancy (To be fully sprinklered NFPA 13D)
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 10/26/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 11/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/8/2023 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 6/15/2023 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 4/10/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/8/2024 | MARCELA FRANQUEZ |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 8/28/2025 | JON MCHUGH |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | JOSE DUARTE-DIAZ |
| Watercourse | Cleared | 1/3/2023 | LEE GUILBEAUX |
| SB8 RUD | Cleared | 3/8/2023 | PATRICIA ALFARO |
| GPI Written Notices | Cleared | 6/15/2023 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 6/15/2023 | MARCELA FRANQUEZ |
| Address approval | Cleared | 6/17/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 6/17/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/21/2023 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 11/6/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 1/22/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/19/2024 | TINA MIRANDA |
| Disturb/Remove Protected Trees | Cleared | 3/19/2024 | ADALBERTO VERA |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: C35492 | 20140 ZIMMERMAN PLACE SANTA CLARITA, CA 91390 |
| Contractor | Bmr Enterprises; Lic. No.: 901546-B | , |
| Contractor | Buildla; Lic. No.: 901546-B | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/12/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 6/17/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 6/21/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | MORRIS JACKSON |
| HVAC-Rough | 11/4/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 11/4/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 11/5/2024 | Corrections Issued | JON MCHUGH |
| Wood Frame | 11/5/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 11/7/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 11/7/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/7/2024 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 1/6/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 1/9/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 1/9/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 1/9/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 1/9/2025 | Corrections Issued | JON MCHUGH |
| Special/Order Compliance | 1/9/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 1/23/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 1/23/2025 | Not Ready for Inspection | JON MCHUGH |
| Special/Order Compliance | 1/23/2025 | Partial Inspection | JUAN ALVARADO |
| Wood Frame | 1/23/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 2/4/2025 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 2/4/2025 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 2/18/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 2/18/2025 | Approved | JON MCHUGH |
| Insulation | 2/18/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 2/18/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2025 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 5/19/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/19/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/19/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/19/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 5/19/2025 | Approved | JON MCHUGH |
| HVAC-Final | 5/19/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/19/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 5/19/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/17/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 7/17/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 7/17/2025 | Approved | JON MCHUGH |
| HVAC-Final | 7/17/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/17/2025 | Approved | JON MCHUGH |
| Final | 8/27/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 8/28/2025 | OK to Issue CofO | JON MCHUGH |