2103 S WALNUT AVE 90291

Certificate Information: 2103 S WALNUT AVE 90291

Application / Permit
22010-10000-05261
Plan Check / Job No.
B22LA21702
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY HOME WITH ATTACHED GARAGE
Permit Issued
Issued on 6/26/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 JOE VO
Corrections Issued 11/6/2022 JOE VO
Quality Review Completed 11/7/2022 GARO TELMI
Plan Check Approved 5/3/2023 JOE VO
Issued 6/26/2023 APPLICANT
CofO in Progress 3/21/2024 HERBERT GIRON
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 11/14/2022 DINAH GARIN
Hydrant and Access approval Cleared 11/18/2022 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 11/22/2022 DINAH GARIN
Sewer availability Cleared 11/22/2022 DINAH GARIN
Low Impact Development Cleared 2/27/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/27/2023 JENSON LEE
Trees in Parkway Cleared 4/10/2023 RICHARD SANCHEZ
Specific Plan Cleared 4/26/2023 PEDRO AYALA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: NA23971       ,
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 200      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan; Lic. No.: NA64238       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 8/31/2023 Partial Approval JESUS RODRIGUEZ
Sewer 8/31/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 8/31/2023 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/8/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 9/8/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Conditional Approval JESUS RODRIGUEZ
Deputy Wood Construction 10/18/2023 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 10/26/2023 Approved HERBERT GIRON
PLUMBING-Rough 10/26/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/30/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/30/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/14/2023 Approved JESUS RODRIGUEZ
Green Building Rough 11/14/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/14/2023 Approved JESUS RODRIGUEZ
Shower Pan 11/14/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/14/2023 Approved JESUS RODRIGUEZ
Insulation 11/20/2023 Approved HERBERT GIRON
Drywall Nailing 11/29/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/29/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 1/25/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 1/29/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/13/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 2/13/2024 Approved HERBERT GIRON
Gas Test 2/14/2024 Approved HERBERT GIRON
PLUMBING-Final 2/14/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/14/2024 SGSOV Approved HERBERT GIRON
HVAC-Final 2/21/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 3/5/2024 No Access for Inspection TEMISTOCLES CAAL
PLUMBING-Final 3/5/2024 No Access for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 3/7/2024 Partial Approval HERBERT GIRON
PLUMBING-Final 3/7/2024 Approved HERBERT GIRON
Service/Power Release 3/7/2024 Approved HERBERT GIRON
Final 3/20/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 3/20/2024 Approved HERBERT GIRON