5800 S BRYNHURST AVE 1-27 90043
Certificate Information: 5800 S BRYNHURST AVE 1-27 90043
- Application / Permit
- 22010-10000-05237
- Plan Check / Job No.
- B22LA21556
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. NEW 4 STORY TYPE VA WITH ROOF DECK 27 UNITS (100% AFFORDABLE HOUSING; 9 VLI AND 17 LI) MIXED USE APARTMENT WITH RETAIL USE PER DENSITY BONUS 12.22.A.25 WITH ADDITIONAL INCENTIVE
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- Issued on 6/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | KEVIN MORALES |
| Corrections Issued | 11/7/2022 | KEVIN MORALES |
| Quality Review Completed | 11/8/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 2/14/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 5/24/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 6/9/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 7/7/2023 | KEVIN MORALES |
| Plan Check Approved | 4/16/2024 | KEVIN MORALES |
| Issued | 6/3/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/27/2023 | RYAN LY |
| Miscellaneous | Cleared | 1/27/2023 | RYAN LY |
| Historic Resource Verification | Cleared | 1/30/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 1/31/2023 | DAVID URITA |
| Bicycle Parking | Cleared | 2/1/2023 | JEREMY CHOK |
| Comm Cor/Mini-Mall | Cleared | 2/1/2023 | NATHAN ROMINE |
| Frnt yard landscape/Water mgmt | Cleared | 2/1/2023 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | WALLIE JONG |
| Opn space landscape/Water mgmt | Cleared | 2/7/2023 | NATHAN ROMINE |
| Trees in Parkway | Cleared | 2/13/2023 | ADALBERTO VERA |
| Highway dedication | Cleared | 2/23/2023 | WALLIE JONG |
| Address approval | Cleared | 3/7/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/6/2023 | LAVEON RIDER |
| Fire Marshal Fire Life Safety | Cleared | 4/19/2023 | MENOA AGHAJANI |
| Building over 36-ft | Cleared | 5/9/2023 | CALOSHA APPROVED |
| Green Code | Cleared | 7/25/2023 | KEVIN MORALES |
| Sewer availability | Cleared | 7/31/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 11/2/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | JEANIE LAM |
| Density Bonus | Cleared | 1/11/2024 | DORIS KWOK |
| SB8 RUD | Cleared | 1/11/2024 | DORIS KWOK |
| Comm Cor/Mini-Mall | Cleared | 1/23/2024 | RYAN LY |
| Specific Plan | Cleared | 1/23/2024 | RYAN LY |
| Miscellaneous | Cleared | 3/12/2024 | RYAN LY |
| DAS Clearance | Cleared | 4/11/2024 | KEVIN MORALES |
Contact Information
| Architect | Youssefzadeh,, Atabak; Lic. No.: C22727 | 1401 WESTWOOD BLVD #320 LOS ANGELES, CA 90024 |
| Contractor | Rimma Construction Inc; Lic. No.: 581895-B | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/17/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 8/20/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/21/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/21/2024 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/4/2024 | Approved | LARRY ARNICK |
| Structural Steel Frame | 9/4/2024 | Partial Approval | LARRY ARNICK |
| Special/Order Compliance | 10/15/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 1/29/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 3/28/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Rough | 4/10/2025 | Partial Approval | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 4/10/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 4/10/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 4/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 4/25/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/25/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 5/9/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 5/9/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 7/1/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 7/1/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 7/22/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 7/24/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 7/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 8/4/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 8/4/2025 | Corrections Issued | RAFAEL CORTES |
| Insulation | 8/7/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 8/14/2025 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 8/26/2025 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 11/26/2025 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/2/2025 | Corrections Issued | RAFAEL CORTES |
| Insulation | 12/9/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 12/16/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 12/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/30/2025 | Partial Approval | LARRY ARNICK |
| Insulation | 1/2/2026 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 1/12/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/26/2026 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 2/11/2026 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 2/17/2026 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 3/2/2026 | Partial Approval | RONALD JIMENEZ |
| Grading Pre-Inspection | 3/16/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 4/9/2026 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 5/15/2026 | Approved | JOEY BUCHANAN |